Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 60certs

PMI PMP Dumps

Page: 1 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 1

The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.

What should the project manager do?

Options:

A.

Inform stakeholders about the delay during project updates.

B.

Determine cross-dependencies and plan a spike in the next sprint.

C.

Discover the gaps in the communications management plan and address them accordingly.

D.

Determine the risks and identify a resolution during the retrospective meeting.

Question 2

A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would notbe able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.

What should the project manager do in this situation?

Options:

A.

Ask the project sponsor to put the project on hold.

B.

Plan to execute the procurement tasks in a virtual environment.

C.

Create a change request to extend the duration of the project.

D.

Review organizational process assets (OPAs) for similar projects.

Question 3

A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During the user story creation phase, the product owner met with multiple stakeholders who had different opinions about the requirements.

How should the project manager address this situation?

Options:

A.

Perform a stakeholder identification analysis.

B.

Ask the product owner to create the backlog.

C.

Limit the participation from stakeholders.

D.

Use a voting system for stakeholders.

Question 4

A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimisticabout the project.

What should the project manager do in this situation?

Options:

A.

Provide team members with specific and clear instructions on the project objectives and tasks.

B.

Communicate the project's impact and plans to engage the project team throughout the project.

C.

Escalate the team's concerns and ask the project sponsor to change the team's composition.

D.

Engage the functional managers to describe the project's impact to the team members directly.

Question 5

In a weekly status meeting with the client, the project manager asks each team member to present how their deliverables are impacting the

customer's final product requirements. Which leadership skill is the project manager applying?

Options:

A.

Ensuring that expectations are clear

B.

Maintaining team spirit and cooperation

C.

Focusing on the important things

D.

Having a holistic and systemic view

Question 6

A highly skilled team resource received a job offer and is leaving the project soon. What should the project manager do to maintain project performancewhile a new team member is being onboarded?

Options:

A.

Offer cross-training and mentoring to the new team member,

B.

Log a risk in the risk register and work with the new team member to mitigate it.

C.

Motivate the new team member to perform.

D.

Share project documents with the new team member,

Question 7

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the differentrequirements?

Options:

A.

Include only the key requirements and keep the stakeholders informed about scope decisions.

B.

Add only the opinions of the team, because they know the objectives of the project.

C.

Include only the common requirements of each stakeholder group in the project goals.

D.

Analyze the interests and influence of stakeholders and evaluate their requirements.

Question 8

From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were veryslow and well outside of the agreed timelines. At the initial kick-off meeting with the same client, how should the project manager approach this issue for thenew project?

Options:

A.

Inform the client that extra resources will be added to give the client more time for reviews.

B.

Update the project risk register with the potential for delays.

C.

Work with the client on an acceptable amount of time for document approval.

D.

Inform the client of their responsibility in relation to document approval.

Question 9

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that the change request was aligned with the project scope.

B.

Requested that the sponsor approved the change request first.

C.

Submitted the change request directly to the CCB.

D.

Assessed the change's overall impact to the project before submission.

Question 10

A project manager has been approached by the project sponsor about adding fo the project scope. How should the project manager accommodate this request?

Options:

A.

Disregard the request since the project scope is finalized.

B.

Create a change request for the change control board (CCB) to review.

C.

Update the project team about the change request.

D.

Adjust the project schedule to accommodate the new project scope requests.

Question 11

A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Talk to the client privately to highlight the situation.

B.

Remove the project team member from all future meetings.

C.

Recommend a performance improvement plan to the project team member.

D.

Explain the impact of the scenario to the project team member.

Question 12

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.

Which three techniques should the project manager use? (Choose 3)

Options:

A.

Iterations and reviews to continuously keep adapting the plan

B.

Gantt chart that includes milestones and deadlines

C.

Rolling wave planning and an adaptive approach

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Relative estimation to determine the task or deliverable sizes

Question 13

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product.

B.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.

C.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work.

D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.

Question 14

A distributed project team wants to use the common ground principle to ensure that they have a common understanding of the scope. The team asks the project lead to set up a

workshop.

What should the project lead do?

Options:

A.

Provide the participants with specific instructions and set the expectations.

B.

Ask the senior members of the development team to elaborate on the scope in detail.

C.

Invite participants to the workshop with sufficient lead time to prepare.

D.

Reduce the number of participants to ensure that consensus is reached easier.

Question 15

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the projectkick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overallproject schedule.

What immediate corrective action should the project manager take?

Options:

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members’ supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Question 16

A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?

Options:

A.

Escalate the issue to the sponsor and debrief them about the situation.

B.

Review the risk management plan to identify the response strategy.

C.

Review the milestone list to determine which tasks can be fast-tracked.

D.

Organize a team meeting to discuss the next course of action.

Question 17

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made arecommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

Options:

A.

Assess the influence and power of the employee to see if the employee will add value.

B.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

C.

Create a salience model to determine if the employee will have influence on the project.

D.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

Question 18

A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.

What should the project manager do?

Options:

A.

Report the issue during the next status meeting at the end of the week.

B.

Escalate the issue to the project sponsor and upper management.

C.

Close out the project and tell the manager to open a service desk ticket.

D.

Log the issue and assign it to the project team member(s).

Question 19

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeksdue to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

Options:

A.

Convince the team member not to leave until the project is completed.

B.

Reach out to the procurement team to hire a substitute for the team member.

C.

Allow senior management to decide how to proceed with the project.

D.

Reach an agreement with the team on how to handle the situation.

Question 20

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for

installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

Options:

A.

Inform the project team only.

B.

Inform the product owner.

C.

Inform the relevant stakeholders.

D.

Inform the project sponsor.

Question 21

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.

This is going to significantly impact the deliverable.

What should the project manager do?

Options:

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

D.

Inform the customer of the impact immediately and prepare for escalation.

Question 22

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements. The former project manager gave the

new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

Options:

A.

Submit a change request to cover extra hours associated with project meetings.

B.

Speak with the client team member about the continuous delays during project meetings.

C.

Update the communications matrix to ensure that client team member is included.

D.

Increase the project meeting frequency and duration to allow for the extra work required.

Question 23

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.

What should the project manager do first?

Options:

A.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

B.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the deliverables.

D.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are submitted.

Question 24

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

Options:

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.

Question 25

A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet

service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now

use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Meet with management about their decision and ask them to get another project manager.

B.

Agree with management and continue working the project management plan.

C.

Replace some of the team members that work virtually to help the company save money.

D.

Evaluate the impact of this decision and communicate with management.

Question 26

Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.

What should the project manager do?

Options:

A.

Request additional resources to be incorporated to the project team.

B.

Observe the project team and give them time to catch up before escalating.

C.

Review the issues and adjust the project plan to give a realistic schedule.

D.

Escalate to the project sponsor and seek alternatives to resolve the issue.

Question 27

A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.

Which document should be used to help avoid this kind of situation?

Options:

A.

Statement of work (SOW)

B.

Escalation process

C.

Communications management plan

D.

Stakeholder register

Question 28

A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.

Which tool is the project manager using?

Options:

A.

Secureanalysis

B.

Time and materials (T&M) contract

C.

Earned value (EV)

D.

Control chart

Question 29

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed

concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

B.

Review the adaptive tools' impact and obtain agreement from the functional manager.

C.

Follow the functional manager's recommendation to implement only predictive tools in the project.

D.

Make the decision on which project approach to use that would best fit the project.

Question 30

A company plans to initiate a project involving a new technology. Approval for the project is required.

What should the project manager do?

Options:

A.

Review the cost and schedule baselines for execution.

B.

Identify the risks in implementing the new technology.

C.

Define change management for the new technology.

D.

Analyze the cost and identify the project benefits.

Question 31

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

Options:

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Question 32

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand

for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Hire a third party who is an expert on the industry's regulations to work out the details.

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Communicate with the industry's regulatory authority to grant the company an exception.

D.

Comply with the regulatory requirements and work to compress the project schedule.

Question 33

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.

What should the project lead do first?

Options:

A.

Discuss with the solution architect

B.

Discuss with the development team

C.

Discuss with the product owner

D.

Discuss with the technical lead

Question 34

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous

project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely

finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Question 35

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Report the disruptive team member to the human resource (HR) department.

B.

Suggest that the team member ignore the disruptive team member and focus only on the work.

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Encourage both team members to meet as soon as possible and resolve the problem.

Question 36

A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

Options:

A.

Project charter

B.

Stakeholder register

C.

Project scope statement

D.

Issue log

Question 37

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Question 38

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the

project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions. @]

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Question 39

A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.

How should the project manager resolve this issue?

Options:

A.

Ask the team to rework the definition of done (DoD) before items can be pulled into the backlog.

B.

Review issues and identify opportunities for improvement that add value to the product.

C.

Gather the project team and product owner to find a solution design.

D.

Assist the team in estimating project tasks such as milestones and story points.

Question 40

A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Implement a project management information system (PMIS).

B.

Encourage better team communication by positioning team members closer together.

C.

Update the communications management plan to ensure correct delivery of the latest version.

D.

Restrict team members from sending the requirements documents via email.

Question 41

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project managermainly make reference to?

Options:

A.

Competencies of team members

B.

Agreed-upon key performance indicators (KPIs)

C.

Feedback from the project sponsor

D.

Input from project stakeholders

Question 42

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the

intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Requested an experienced resource as a replacement

B.

Convinced the critical resource to remain on the project

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Question 43

During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract

end date. The contract is clear about the expiration of the service.

How should the project manager address this situation in order to close the project?

Options:

A.

Issue a change request and activate the formal change control process to address the situation.

B.

Escalate the request to the functional manager to approve the additional service hours.

C.

Deny the request and include it in lessons learned documentation for the next contract renewal.

D.

Accept the client's proposal to use the service until the additional hours are exhausted.

Question 44

A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the

transformation manager arises.

What should the project manager do to manage this?

Options:

A.

Analyze the context of the issue.

B.

Evaluate the influence of the parties involved.

C.

Lead the parties to find a compromise.

D.

Escalate the problem to the project sponsor.

Question 45

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what thetakeholders are currently asking for. This is because the initial requirements werechanged during a previousmeeting.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured changing stakeholder needs and requests were properly monitored

B.

Ensured that communications were sent to all stakeholders when requirements change

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured procurement contracts were able be canceled when situations like this arise

Question 46

An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.

What action should the project manager take?

Options:

A.

Work with the IT team to prioritize the validation and release of the new features.

B.

Escalate the issue from the IT team to management and get the validation prioritized.

C.

Request the IT team to immediately release the product and then validate the features.

D.

Deliver the features when the IT team is able to validate them.

Question 47

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team

members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

Options:

A.

Draft a points system to allocate a portion of the money for each resource.

B.

Arrange a luncheon for all team members and include team-building sessions.

C.

Meet with the team members and ask them how to spend the reward.

D.

Allocate the reward to the team leaders to spend on the team as they see fit.

Question 48

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the

project.

What should the project manager do?

Options:

A.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain.

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

Question 49

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue, however, the

concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Risk register

C.

Issue log

D.

Scope statement

Question 50

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Question 51

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in

the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for

the second milestone are changed.

Which two actions should the project manager take? (Choose 2)

Options:

A.

Ask the customer for their priorities regarding the requirements for the second milestone.

B.

Convince the customer to leave the second milestone in place and not change it.

C.

Tell the customer that moving the milestone has a very high impact on the cost of the project.

D.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

E.

Escalate the issue to upper management to resolve the problem, and suggest a plan.

Question 52

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The

licensing cost is significant.

What should the project manager do next?

Options:

A.

Escalate the licensing issue to the product owner.

B.

Evaluate the impact of nonrenewal of the license.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Question 53

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

B.

Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

C.

Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Question 54

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently

implemented.

What should the project manager do?

Options:

A.

Escalate the team member's performance to the project sponsor.

B.

Ask the team member to learn the new system as on-the-job training.

C.

Issue a change request to extend the project schedule.

D.

Assign an experienced resource to support the team member.

Question 55

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Reinforce the ground rules for standup meetings with the entire team.

B.

Schedule the meeting at the end of the day to accommodate everyone.

C.

Speak with the team member directly to reinforce the ground rules.

D.

Ignore the situation since the team member is accomplishing their deliverables.

Question 56

A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered.

The project manager organized a few spikes to resolve this conflict.

What should the project manager do next?

Options:

A.

Ask the project sponsor to decide which option should be implemented.

B.

Organize a multivoting event to achieve consensus of the whole team.

C.

Allow the team to decide on their own which option should be implemented.

D.

Organize more spike events until consensus of the team is reached.

Question 57

An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the

second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer.

B.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

C.

Split the feature into smaller subfeatures, implement them, and then deliver them incrementally in multiple iterations.

D.

Ask the customer to simplify the feature so that it can be implemented in one iteration.

Question 58

project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

Options:

A.

The deliverables that are performing well and those that need more work.

B.

Specialized reports created specifically for the meeting as per directions from the project sponsor.

C.

Potential changes to the project's strategy and the feedback from senior executives.

D.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.

Question 59

In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What shouldthe project manager do in thissituation?

Options:

A.

Discourage this request, as it is for the management team.

B.

Encourage the team lead to make decisions.

C.

Discourage them as conflicts may be created.

D.

Encourage the team members to make decisions.

Question 60

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.

What should the project manager do?

Options:

A.

Cancel the iteration and add the requested changes.

B.

Continue the iteration and add the requested changes.

C.

Continue the iteration and review the change with the customer.

D.

Cancel the iteration and meet with the product owner.

Question 61

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.

How should the project manager handle the situation?

Options:

A.

Have a discussion with the project sponsor and cancel the project.

B.

Have a discussion with the sponsor and recommend the project business value be reassessed.

C.

Remove the items no longer applicable from the backlog and present the backlog to the project team.

D.

Continue working on the defined scope and review the risk matrix.

Question 62

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that

having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the scrum master to attend the workshops.

B.

Ask the Scrum team members to share retrospectives.

C.

Invite the Scrum team members as mandatory participants.

D.

Invite the Scrum team members as optional participants

Question 63

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?

Options:

A.

Compare the cost of improving quality against the cost of failure and adjust the budget.

B.

Help the team create the definition of done (DoD) to improve delivery quality. 0 2 Add testing items to the backlog to assess quality periodically. oO

C.

Expand the team in order to improve the quality of the project.

Question 64

A project manager received a request to add features and functions to the project after the scope had already been established. What should the projectmanager do?

Options:

A.

Follow the stakeholder engagement process.

B.

Follow the risk management process.

C.

Follow the change management process.

D.

Follow the requirements management process.

Question 65

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access

to water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Question 66

A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would liketo launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.

Which project approach suits the scenario?

Options:

A.

Execute it as a Scrum project.

B.

Execute it as a predictive project.

C.

Execute it as a project with stage gates.

D.

Execute it using the same approach as the reference project.

Question 67

A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.

What should the project manager have done to prevent this situation?

Options:

A.

Sought and implemented alternative ways to track progress and impediments to identify potential threats

B.

Considered historical data from previous projects with similar impediments to help identify the possible solutions

C.

Provided technical training to the team in advance to ensure the team had high-level technical skills

D.

Developed a risk response plan that would have provided options and strategies regarding project risk exposure

Question 68

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?

Options:

A.

Ask the sponsor to add experienced professionals to the team.

B.

Approve the appropriate training program for team members.

C.

Provide team members with the necessary coaching and mentoring.

D.

Assign a dedicated resource to check the quality of each deliverable.

Question 69

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the

complexity of the work was underestimated.

What should the project manager do?

Options:

A.

Update the issue log and escalate it to the project sponsor.

B.

Ask to replace some team members with more experienced ones.

C.

Meet with the team to review internal actions to resolve the situation.

D.

Ask the technical manager to help the team with the issue.

Question 70

During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?

Options:

A.

Ask the project sponsor to make the decision about the design features.

B.

Call a stakeholder meeting along with team members and seek consensus.

C.

Ask stakeholders to reduce the scope in order to meet project deadlines.

D.

Review the design with the team members and propose a new launch date.

Question 71

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.

Send a daily retrospective report to all team members instead of holding standup meetings.

B.

Engage the project team in implementing and improving key aspects of the standup meetings.

C.

Include a daily brainstorming session in the standup meetings to resolve pending issues.

D.

Ask the product owner to remove team members who do not comply with standup meeting rules.

Question 72

A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan.

B.

Add the needed manual and update the risk log.

C.

Review the terms and conditions of the contract.

D.

Submit a change request to include the manual.

Question 73

A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know

how frequently the risks are being reviewed.

Which document project manager should check first?

Options:

A.

Risk management plan

B.

Risk register

C.

Issue log

D.

Risk report

Question 74

vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified

an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.

What should the project manager do next?

Options:

A.

Perform a cost-benefit analysis.

B.

Implement risk responses.

C.

Perform Integrated Change Control.

D.

Request a replacement resource.

Question 75

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The

project manager starts to present the budget, but the CEO suddenly asks to end the meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.

B.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.

C.

Reviewed the communications management plan before inviting an external client representative to the meeting.

D.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.

Question 76

A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.

To what level should the project manager decompose their project?

Options:

A.

To the level where the highest level of quality is maintained

B.

To the lowest level where cost and duration can be estimated and managed

C.

To level four of the schedule for bridge construction

D.

To the level where the bridge can be constructed safely

Question 77

A global program is being kicked off, and various distributed teams are involved in delivering the initiative.Besides planning and executingthe scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Videoconferencing

B.

Chat conversations

C.

Encrypted emails

D.

Phone conversations

Question 78

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?

Options:

A.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

B.

Create a reward system granting incentives to the team members who are able to catch more defects.

C.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems.

D.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones.

Question 79

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

Options:

A.

Empower the team members to do their work.

B.

Inform the project sponsor about this situation.

C.

Work with the team to develop a risk response plan.

D.

Send an email to human resources (HR) about this situation.

Question 80

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

B.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

C.

Keep the task assignments unchanged since the project management plan has been approved.

D.

Review the work allocation and reassign some tasks to shorten the critical path.

Question 81

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified

the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Conducted periodic reviews with the manager on resource availability.

B.

Defined the skill requirements more clearly in the scope statement.

C.

Consulted with the installation team on a regular basis to check for conflicts.

D.

Asked the manager to follow the agreed-upon resource management plan.

Question 82

During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?

Options:

A.

Identify the resources that were responsible for the deliverable and request a team development plan.

B.

Update the risk register and implement the approved risk response plan for quality deviations.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the corrective actions.

D.

Submit a change request to update the project quality requirements for the involved project deliverable.

Question 83

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is

below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Apply an agile approach to help improve team performance.

B.

Schedule a meeting and communicate the performance concern to the team.

C.

Study and determine the appropriate leadership style suitable for the team.

D.

Hirea project team leader who can influence the project team members.

Question 84

During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is

concerned about working overtime.

What should the project manager do to motivate the team?

Options:

A.

Crash the project schedule to ensure completion on time.

B.

Meet with the team members to review their roles and responsibilities.

C.

Introduce team-building activities to improve team performance.

D.

Negotiate with the client to reduce the changes in requirements.

Question 85

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.

Which of the documents was likely missed or outdated?

Options:

A.

Stakeholder Register

B.

Business Documentation

C.

Project Charter

D.

Risk Register

Question 86

A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the keystakeholders.

What should the project manager do first?

Options:

A.

Agree on quality standards with the key stakeholders.

B.

Engage experienced key stakeholders in the implementation of the project.

C.

Develop a requirements traceability matrix.

D.

Review the test and inspection plan with the key stakeholders.

Question 87

A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project, and their resistance to the project may affect the project

deadline.

What two actions should the project manager take? (Choose two.)

Options:

A.

Analyze the situation and find out what is causing the neighborhood's negative attitude.

B.

Ask the customer to extend the project deadline to allow time for conflict resolution.

C.

Ask the mayor of the city to use their authority to stop neighborhood resistance.

D.

Set up a meeting with neighborhood representatives to win their cooperation.

E.

Send letters to the neighbors and ask them kindly not to disturb the project.

Question 88

A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to

obtain the main message and take action.

What should the project manager do to avoid similar complaints?

Options:

A.

Send a shorter daily report to this steering committee member.

B.

Demonstrate the weekly reports in a presentation for the steering committee member.

C.

Verify the information needed for steering committee members.

D.

Present the status at a weekly meeting with the steering committee.

Question 89

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the

project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are

well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.

What should the project manager do?

Options:

A.

Review the resources allocated to the project and change accordingly.

B.

Review and amend the processes to ensure only value-adding activities are present.

C.

Update the variation register to account for the extended project time.

D.

Update the schedule to account for the unexpected delays in the project tasks.

Question 90

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team to accelerate the iterations and avoid interruptions.

B.

Verify team performance and ask for improvement during daily standup meetings.

C.

Recommend that the project sponsor increases the budget to bring new resources.

D.

Discuss the problem with the team and decide how to do the work together.

Question 91

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not

have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

B.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place.

D.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

Question 92

A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of

the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder, and include the stakeholder’s needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Question 93

A project manager is building a team to work on a service integration project that will transition technology management services from company A tocompany B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, havedifferent types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

Options:

A.

Organize the team members into several kick-off sessions based on technology type.

B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.

C.

Ask the human resources (HR) department to arrange interview meetings to select the team.

D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.

Question 94

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.

What shouldthe project manager do next?

Options:

A.

Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.

B.

Request that the offices in overseas locations work overtime to mitigate schedule slippages.

C.

Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.

D.

Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.

Question 95

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

B.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

C.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

D.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

Question 96

An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.

What should the project lead do?

Options:

A.

Tell the stakeholder that a new report will be produced at the end of the iteration.

B.

Explain to the stakeholder that the key indicators are by iteration.

C.

Ask the product owner to develop the new report based on the iteration information.

D.

Develop the requested report based on the iteration information.

Question 97

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

C.

Escalate to the project management office (PMO) and request a solution for the requirements

D.

Allow the project team to decide what is the most appropriate requirement to follow

Question 98

A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the

system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

include knowledge transfer sessions between the project and operations team at every stage

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure

Question 99

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages.

This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

Options:

A.

Schedule a communications control board meeting.

B.

Implement team colocation to improve communication.

C.

Identify the root cause of communication issues,

D.

Initiate daily communication of project progress.

Question 100

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?

(Choose three)

Options:

A.

Adjust the project management plan to include the changes in scope.

B.

Continue the execution as planned and defer the changes to a future phase.

C.

Highlight the impacts of the changes during the next project meeting.

D.

Schedule a meeting with the customer to align the approach.

E.

Update the relevant project documents with this obstacle.

Question 101

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do toimprove project performance?

Options:

A.

Empower the team members to remove obstacles and blockers.

B.

Address and remove obstacles and blockers for the team.

C.

Ask stakeholders to communicate with the team directly.

D.

Add blockers to the issue log and risk management plan.

Question 102

A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.

What should the project manager do to improve communication among the team?

Options:

A.

Setup a team communications management plan for the company and team members to follow immediately.

B.

Explain the benefits of common working hours to aid better communication among the project team.

C.

Share a contact log document for all the team members to make communication easier.

D.

Arrange for some initial face-to-face team meetings for the project team to meet each other.

Question 103

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.

During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all the required approvals were received per the organizational procedures

B.

Ensured that all defects identified during testing were resolved before implementation

C.

Ensured that all of the required tasks identified in the scope were completed successfully

D.

Ensured that all documentation was completed post implementation before closing the project

Page: 1 / 26
Total 354 questions