The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?
A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would notbe able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.
What should the project manager do in this situation?
A project manager is working on a project to scale an operation globally. This endeavor required multiple interviews with various stakeholders. During the user story creation phase, the product owner met with multiple stakeholders who had different opinions about the requirements.
How should the project manager address this situation?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimisticabout the project.
What should the project manager do in this situation?
In a weekly status meeting with the client, the project manager asks each team member to present how their deliverables are impacting the
customer's final product requirements. Which leadership skill is the project manager applying?
A highly skilled team resource received a job offer and is leaving the project soon. What should the project manager do to maintain project performancewhile a new team member is being onboarded?
A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the differentrequirements?
From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were veryslow and well outside of the agreed timelines. At the initial kick-off meeting with the same client, how should the project manager approach this issue for thenew project?
The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.
What should the project manager have done to avoid this situation?
A project manager has been approached by the project sponsor about adding fo the project scope. How should the project manager accommodate this request?
A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?
The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.
Which three techniques should the project manager use? (Choose 3)
An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.
How should this situation be handled?
A distributed project team wants to use the common ground principle to ensure that they have a common understanding of the scope. The team asks the project lead to set up a
workshop.
What should the project lead do?
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the projectkick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overallproject schedule.
What immediate corrective action should the project manager take?
A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on theproject due to a lack of resources. What should the project manager do next?
A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made arecommendation regarding the project. The project charter was recently approved.
How should the project manager address the employee's request?
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to allstakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeksdue to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?
A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers arranged time off to allow time for
installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.
What does the project manager need to do now?
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.
This is going to significantly impact the deliverable.
What should the project manager do?
A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements. The former project manager gave the
new project manager a complete list of people to communicate with, and this client team member is not on it.
What should the project manager do?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.
What should the project manager do first?
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet
service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now
use a system running on a conventional dial-up service.
What should the project manager do next?
Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.
What should the project manager do?
A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.
Which document should be used to help avoid this kind of situation?
A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.
Which tool is the project manager using?
A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing
adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed
concerns about the use of new tools on such an important project.
What should the project manager do?
A company plans to initiate a project involving a new technology. Approval for the project is required.
What should the project manager do?
A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?
A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand
for this product and wants it to launch as soon as possible.
What should the project manager do to realize this opportunity?
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.
What should the project lead do first?
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous
project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely
finished in 8 months.
What should the new project manager do?
While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.
How should the project manager handle this situation?
A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the
project manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.
How should the project manager resolve this issue?
A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project managermainly make reference to?
An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the
intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract
end date. The contract is clear about the expiration of the service.
How should the project manager address this situation in order to close the project?
A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the
transformation manager arises.
What should the project manager do to manage this?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what thetakeholders are currently asking for. This is because the initial requirements werechanged during a previousmeeting.
What should the project manager have done to avoid this situation?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team. Due to other priorities for the IT team, the releases are delayed.
What action should the project manager take?
A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings among team
members. The project sponsor has allocated a monetary award.
How should the project manager utilize the award?
A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the
project.
What should the project manager do?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue, however, the
concern could not be addressed.
In which project document should the project manager record the concern?
A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.
What should the project manager do?
In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in
the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for
the second milestone are changed.
Which two actions should the project manager take? (Choose 2)
In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The
licensing cost is significant.
What should the project manager do next?
A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently
implemented.
What should the project manager do?
One of the team members is always late to the daily standup meeting. What should the project manager do?
A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered.
The project manager organized a few spikes to resolve this conflict.
What should the project manager do next?
An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the
second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What shouldthe project manager do in thissituation?
After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.
What should the project manager do?
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.
How should the project manager handle the situation?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that
having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?
A project manager received a request to add features and functions to the project after the scope had already been established. What should the projectmanager do?
A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access
to water. What should the project manager do next?
A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would liketo launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.
Which project approach suits the scenario?
A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.
What should the project manager have done to prevent this situation?
An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the
complexity of the work was underestimated.
What should the project manager do?
During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.
How should the project manager improve this situation with the project team?
A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know
how frequently the risks are being reviewed.
Which document project manager should check first?
vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified
an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The
project manager starts to present the budget, but the CEO suddenly asks to end the meeting.
What should the project manager have done to avoid this situation?
A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.
To what level should the project manager decompose their project?
A global program is being kicked off, and various distributed teams are involved in delivering the initiative.Besides planning and executingthe scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?
In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified
the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?
During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is
below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is
concerned about working overtime.
What should the project manager do to motivate the team?
During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user partywas not included in any of therequirements collection communications.
Which of the documents was likely missed or outdated?
A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the keystakeholders.
What should the project manager do first?
A large project is affecting the neighborhood in which it is located. The neighbors are not satisfied with the project, and their resistance to the project may affect the project
deadline.
What two actions should the project manager take? (Choose two.)
A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to
obtain the main message and take action.
What should the project manager do to avoid similar complaints?
A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the
project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are
well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.
What should the project manager do?
A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.
What strategy should the project manager implement to deal with this situation?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not
have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of
the stakeholders highlighted that they were unaware of the status for the project deliverables.
What should the project manager do first?
A project manager is building a team to work on a service integration project that will transition technology management services from company A tocompany B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, havedifferent types of technology backgrounds, and use different approaches for work.
How should the project manager build a cohesive, high-performing team?
On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.
What shouldthe project manager do next?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.
What should the project lead do?
A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the
system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages.
This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?
During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?
(Choose three)
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do toimprove project performance?
A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.
What should the project manager do to improve communication among the team?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.
During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?