Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Online PMP Questions Video

Page: 25 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 97

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

C.

Escalate to the project management office (PMO) and request a solution for the requirements

D.

Allow the project team to decide what is the most appropriate requirement to follow

Question 98

A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the

system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

Options:

A.

Create a lessons learned register to include operations team training for future projects.

B.

include knowledge transfer sessions between the project and operations team at every stage

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure

Question 99

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages.

This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

Options:

A.

Schedule a communications control board meeting.

B.

Implement team colocation to improve communication.

C.

Identify the root cause of communication issues,

D.

Initiate daily communication of project progress.

Question 100

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue?

(Choose three)

Options:

A.

Adjust the project management plan to include the changes in scope.

B.

Continue the execution as planned and defer the changes to a future phase.

C.

Highlight the impacts of the changes during the next project meeting.

D.

Schedule a meeting with the customer to align the approach.

E.

Update the relevant project documents with this obstacle.

Page: 25 / 26
Total 354 questions