Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Project-Management-Professional PMP Updated Exam

Page: 14 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 53

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Options:

A.

Use the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.

B.

Meet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.

C.

Follow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.

D.

Coach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.

Question 54

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently

implemented.

What should the project manager do?

Options:

A.

Escalate the team member's performance to the project sponsor.

B.

Ask the team member to learn the new system as on-the-job training.

C.

Issue a change request to extend the project schedule.

D.

Assign an experienced resource to support the team member.

Question 55

One of the team members is always late to the daily standup meeting. What should the project manager do?

Options:

A.

Reinforce the ground rules for standup meetings with the entire team.

B.

Schedule the meeting at the end of the day to accommodate everyone.

C.

Speak with the team member directly to reinforce the ground rules.

D.

Ignore the situation since the team member is accomplishing their deliverables.

Question 56

A project manager is performing the role of scrum master for a team of developers. There is a conflict among the developers, generated by differences in how a feature can be delivered.

The project manager organized a few spikes to resolve this conflict.

What should the project manager do next?

Options:

A.

Ask the project sponsor to decide which option should be implemented.

B.

Organize a multivoting event to achieve consensus of the whole team.

C.

Allow the team to decide on their own which option should be implemented.

D.

Organize more spike events until consensus of the team is reached.

Page: 14 / 26
Total 354 questions