Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Ace Your PMP Project-Management-Professional Exam

Page: 35 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 137

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

Options:

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Question 138

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

Options:

A.

Consult the previous project manager to discuss how they managed these questions.

B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.

C.

Email the company vision to the engineers and tell them they need to meet deadlines

D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.

Question 139

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Question 140

A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?

Options:

A.

Company's historical organizational project artifacts

B.

Company's project responsibility assignment matrix (RAM)

C.

Company's resource management plan

D.

Company's resource calendars

Page: 35 / 152
Total 2040 questions