Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 60certs

Exactprep PMP Questions

Page: 3 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 9

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept thisrejection and does not want tocontinue the project without the change.

What should the project manager have done to avoid this situation?

Options:

A.

Ensured that the change request was aligned with the project scope.

B.

Requested that the sponsor approved the change request first.

C.

Submitted the change request directly to the CCB.

D.

Assessed the change's overall impact to the project before submission.

Question 10

A project manager has been approached by the project sponsor about adding fo the project scope. How should the project manager accommodate this request?

Options:

A.

Disregard the request since the project scope is finalized.

B.

Create a change request for the change control board (CCB) to review.

C.

Update the project team about the change request.

D.

Adjust the project schedule to accommodate the new project scope requests.

Question 11

A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Talk to the client privately to highlight the situation.

B.

Remove the project team member from all future meetings.

C.

Recommend a performance improvement plan to the project team member.

D.

Explain the impact of the scenario to the project team member.

Question 12

The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.

Which three techniques should the project manager use? (Choose 3)

Options:

A.

Iterations and reviews to continuously keep adapting the plan

B.

Gantt chart that includes milestones and deadlines

C.

Rolling wave planning and an adaptive approach

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Relative estimation to determine the task or deliverable sizes

Page: 3 / 26
Total 354 questions