Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Last Attempt PMP Questions

Page: 43 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 169

A project manager is leading a contract for a new market that was awarded to their company. The client has the desire to jump-start the market with informal sector traders. What should the project manager do?

Options:

A.

Plan the project in phases, starting with the informal sector, to deliver business value quickly

B.

Divide the project team into groups to execute as small parallel projects, including the informal sector

C.

Gather requirements and convert them into backlog items to quickly deliver value

D.

Execute the projects simultaneously following the project schedule and the communications management plan

Question 170

During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed and impacts the project schedule. What should the project manager do?

Options:

A.

Work with the project team to find a compromise solution that suits both departments

B.

Schedule a meeting with the project sponsor to seek advice on the approach of both departments

C.

Arrange a meeting with the two departments to understand their differences and address their needs

D.

Assess the risk of postponing this specific solution and advise both departments of the delay

Question 171

A project is in its first of six iterations. The project team realizes that a key deliverable is dependent on the acquisition of a new device. The vendor is new to the organization and does not have a long history in the market. What should the project manager do first?

Options:

A.

Register the risk and provide appropriate response options.

B.

Register the risk and prioritize the implementation strategy.

C.

Register the risk and escalate it to the procurement team.

D.

Register the risk and escalate it to the project sponsor.

Question 172

A project has a schedule performance index (SPI) of 0.75 and a cost performance index (CPI) of 1.1. As a result, the project manager is considering either fast-tracking or crashing the project schedule to bring the project back on track again. What could be a secondary result of these actions?

Options:

A.

A decrease in the project cost

B.

An increase in the project risk

C.

Additional project scope

D.

Additional resources

Page: 43 / 160
Total 2134 questions