Explanation: According to the PMBOK Guide, 7th edition, project planning is the process of establishing the scope, objectives, and course of action for the project. Project planning involves developing the project management plan, which is a document that describes how the project will be executed, monitored, and controlled. Project planning also involves engaging the project stakeholders, identifying the project requirements, defining the project scope, estimating the project resources, creating the project schedule, determining the project budget, assessing the project risks, and establishing the project governance. Project planning is essential for the project success, as it provides the basis for project performance measurement and control. In this question, the project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to water. The question asks what the project manager should do next.
Based on this information, the best answer is option B, which is to start project planning and develop the project management plan. This is because starting project planning and developing the project management plan is the logical and necessary next step for the project manager after being assigned to the project. Starting project planning and developing the project management plan can help the project manager to define the project scope, objectives, and course of action, as well as to align the project with thestakeholder needs and expectations. Starting project planning and developing the project management plan can also help the project manager to address the project urgency, as it can enable the project manager to prioritize the project activities, allocate the project resources, and manage the project risks.
Option A, which is to hire local contractors who are familiar with the environment, is not a good answer. This is because hiring local contractors who are familiar with the environment may not be the next step for the project manager, as it may require some prior planning and analysis. Hiring local contractors who are familiar with the environment may involve defining the project procurement strategy, conducting market research, preparing the procurement documents, soliciting bids or proposals, evaluating and selecting vendors, and negotiating and signing contracts. Hiring local contractors who are familiar with the environment may also depend on the availability, suitability, and affordability of the local contractors, as well as the legal and ethical implications of the procurement process.
Option C, which is to face the challenge immediately and start sending relief to the town, is not a good answer. This is because facing the challenge immediately and starting sending relief to the town may not be the next step for the project manager, as it may not be part of the project scope or objectives. Facing the challenge immediately and starting sending relief to the town may involve providing humanitarian aid, such as food, water, medicine, or shelter, to the affected community. Facing the challenge immediately and starting sending relief to the town may also require coordination and collaboration with other organizations, such as government agencies, non-governmental organizations, or international bodies, that are involved in the relief efforts. Facing the challenge immediately and starting sending relief to the town may also entail additional risks and challenges, such as security, logistics, or cultural issues, that may affect the project delivery.
Option D, which is to process a change request for additional funding due to project urgency, is not a good answer. This is because processing a change request for additional funding due to project urgency may not be the next step for the project manager, as it may not be justified or approved. Processing a change request for additional funding due to project urgency may involve documenting the rationale, impact, and benefits of the change, as well as submitting the change request to the appropriate authority for review and approval. Processing a change request for additional funding due to project urgency may also depend on the availability, allocation, and distribution of the project funds, as well as the alignment of the change with the project scope, schedule, quality, and risks. References: PMBOK Guide, 7th edition, Chapter 5: Planning1; Chapter 6: Project Management Plan2; PMI, 2023, PMP Exam Content Outline, Domain II: Process, Task 2: Plan and manage project/phase scope3.