Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Selected PMP Project-Management-Professional Questions Answers

Page: 17 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 65

During a project ' s execution phase, the team faced a setback in one of the deliveries and was asked to come up with a new plan. All team members joined a meeting to address the issue and, after a while, the project manager observed that two members of the team were just agreeing with anything that was proposed even though they were opposed to the outcome.

What conflict resolution style were the team members adopting?

Options:

A.

Avoidant style

B.

Combative style

C.

Collaborative style

D.

Accommodative style

Question 66

A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.

How should the project manager improve the team ' s understanding?

Options:

A.

Involve team members in stakeholder analysis and engagement.

B.

Invite all stakeholders to progress meetings to avoid ambiguity.

C.

Ensure team members have access to a well-written requirements traceability matrix.

D.

Engage with the project sponsor and ensure the product backlog is correct and up to date.

Question 67

The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.

How should the project manager proceed?

Options:

A.

Call and apologize to the team members and provide an update on how this issue was caused.

B.

Review the communications management plan and stakeholder engagement plan for the project.

C.

Request the operations support team to troubleshoot and determine the root cause of the issue.

D.

Obtain a list of the affected stakeholders and email the current status information to them.

Question 68

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.

What should the project manager do to manage such a situation for upcoming phases?

Options:

A.

Revise the project schedule to accommodate fixing discovered issues.

B.

Ensure customer validation occurs more frequently during the life cycle of the project.

C.

Review the customer validation team ' s test plan early in the life cycle.

D.

Ask the project team to increase unit testing of the deliverables.

Page: 17 / 165
Total 2196 questions