Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Selected PMP Project-Management-Professional Questions Answers

Page: 17 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 65

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access

to water. What should the project manager do next?

Options:

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Question 66

A project for a new product launch is in a very initial stage and the requirements are evolving. Due to stiff competition in the market, the customer would liketo launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year.

Which project approach suits the scenario?

Options:

A.

Execute it as a Scrum project.

B.

Execute it as a predictive project.

C.

Execute it as a project with stage gates.

D.

Execute it using the same approach as the reference project.

Question 67

A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found atechnical impediment that put the project delivery in jeopardy overnight.

What should the project manager have done to prevent this situation?

Options:

A.

Sought and implemented alternative ways to track progress and impediments to identify potential threats

B.

Considered historical data from previous projects with similar impediments to help identify the possible solutions

C.

Provided technical training to the team in advance to ensure the team had high-level technical skills

D.

Developed a risk response plan that would have provided options and strategies regarding project risk exposure

Question 68

An experienced project manager is leading an enthusiastic team but realizes the team lacks the experience to complete thejob successfully. What shouldthe project manager do to reduce the risk of project failure?

Options:

A.

Ask the sponsor to add experienced professionals to the team.

B.

Approve the appropriate training program for team members.

C.

Provide team members with the necessary coaching and mentoring.

D.

Assign a dedicated resource to check the quality of each deliverable.

Page: 17 / 26
Total 354 questions