Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Passing Score

Page: 13 / 14
Total 187 questions

Project Management Professional (PMP) July 2026 Update Questions and Answers

Question 49

According to the Alpha project’s risk management report, which risks should the project manager prioritize?

(Refer to Alpha Project — Risk Management Report exhibit.)

Options:

A.

1, 2, 9

B.

4, 14, 15

C.

8, 18, 20

D.

17, 19, 5

Question 50

A project manager conducts weekly virtual project meetings with all stakeholders to keep them updated on project progress and discuss key issues. Some stakeholders appear disengaged or are occupied with other work during the meetings. Other stakeholders have stopped attending.

What should the project manager do?

Options:

A.

Review engagement methods and ensure meetings are tailored to the stakeholders’ communication needs.

B.

Reinforce the ground rules to ensure full attendee participation during the stakeholder meetings.

C.

Update the issue log and lessons learned register to ensure this is captured for future stakeholder meetings.

D.

Distribute the agenda before meetings to ensure stakeholders are updated about the need for increased engagement.

Question 51

A digital health development team is tasked with designing a new product, which is a pioneering effort for the organization and one of the few available in a

‘competitive market. The planning and auditing processes have been notably time-consuming. The development team has reported limited rework and minimal

customer complaints; however, the current budget significantly exceeds the typical project baselines for previous product development initiatives within the

organization. The project manager is currently analyzing the total cost of quality for the project.

What should the project manager do?

Options:

A.

Maintain the planned investment, appraisal, and prevention cost plan to reduce failure costs.

B.

Increase prevention costs to maintain project stability, reduce failure costs, and support the pace of change.

C.

Reduce internal costs to increase time to deliver value on schedule and on budget and reduce failure costs.

D.

Increase internal failure costs to detect defects early and minimize risks.

Question 52

A project manager is identifying stakeholders for a research project. The stakeholders that are included are individuals from academia, industry, and government.

What should the project manager do once stakeholders are identified?

Options:

A.

Communicate with the stakeholders about the progress of the project on a regular basis.

B.

Conduct facilitation sessions with the stakeholders to understand and align their expectations.

C.

Focus on key stakeholders who are critical to the project.

D.

Engage the stakeholders based on their influence on the project.

Page: 13 / 14
Total 187 questions