Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Project-Management-Professional PMP Passing Score

Page: 13 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 49

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue, however, the

concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Risk register

C.

Issue log

D.

Scope statement

Question 50

A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master'sprogram will coincide with thelast phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

B.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

C.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Question 51

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter. The customer wants to show their stakeholders a tangible outcome in

the first quarter and wants to move the second milestone to the first quarter. The project manager explains to the customer that it is not feasible unless the requirements for

the second milestone are changed.

Which two actions should the project manager take? (Choose 2)

Options:

A.

Ask the customer for their priorities regarding the requirements for the second milestone.

B.

Convince the customer to leave the second milestone in place and not change it.

C.

Tell the customer that moving the milestone has a very high impact on the cost of the project.

D.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

E.

Escalate the issue to upper management to resolve the problem, and suggest a plan.

Question 52

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The

licensing cost is significant.

What should the project manager do next?

Options:

A.

Escalate the licensing issue to the product owner.

B.

Evaluate the impact of nonrenewal of the license.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Page: 13 / 26
Total 354 questions