Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Passing Score

Page: 13 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 49

Four new teams have been formed to develop a new product. Several team members ask the project manager who will integrate the different work streams into one backlog.

What should the project manager do?

Options:

A.

Create integration tasks and schedule an additional team meeting following the standup meeting to plan the integration.

B.

Advise the teams to work individually and organize an integration iteration every four development sprints.

C.

Instruct the team to use the kanban board daily to facilitate alignment of their work item list, allowing them to do their best work.

D.

Advise the teams to collaborate with the product owner in prioritizing the stories, considering dependencies and preventing overlap.

Question 50

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?

Options:

A.

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.

B.

Discuss the issue with the team so the product manager can understand the trade-offs.

C.

Suggest the team and product manager go with the faster approach, reducing the scope.

D.

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor ' s guidance.

Question 51

A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?

Options:

A.

Ask the team to adapt based on their current resources.

B.

Plan a meeting with the stakeholders to get more resources.

C.

Replan the upcoming deliverables based on the available tools.

D.

Ask the project sponsor to provide the needed resources.

Question 52

A project manager was recently assigned to work on a hybrid project. After being a part of the project team for a couple of months, the project manager realizes that parts of this project depend on other organizational projects. These dependencies have not been identified.

What should the project manager do first?

Options:

A.

Brainstorm with the team and stakeholders to identify the risks.

B.

Review the risk register and update it if necessary.

C.

Host a retrospective session with the agile team.

D.

Ignore the concerns for now and review them in 3 months.

Page: 13 / 165
Total 2196 questions