Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMP VCE Exam Download

Page: 31 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 121

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

Options:

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Question 122

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Question 123

A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water

What caused this situation to occur?

Options:

A.

The risk analysis was inadequate

B.

The project was completed behind schedule

C.

The requirements gathering was inadequate

D.

The project was delivered above budget

Question 124

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

Options:

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Page: 31 / 165
Total 2196 questions