Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Based on Real Exam Environment

Page: 9 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 33

A project manager is in the process of authoring the communications management plan for a new project. One of the project ' s stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.

What should the project manager do?

Options:

A.

Ensure that social media posts related to the project are removed.

B.

Ensure that sensitive information is not included in stakeholder updates.

C.

Review social media access and restrict it to ensure confidentiality.

D.

Review the protocols and security measures to ensure confidentiality.

Question 34

An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.

What should the project manager take into account first when building the schedule for this new project?

Options:

A.

The benchmarked velocities of the previously completed projects

B.

The benchmarked baselines of the previously completed projects

C.

The compliance needs and categories of the new project

D.

The compliance measurement criteria of the new project

Question 35

An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

Options:

A.

Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.

B.

Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.

C.

Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.

D.

Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.

Question 36

A company is experiencing a high rate of rejected project deliverables. The project manager is requested to suggest a solution to improve quality.

What should the project manager suggest?

Options:

A.

Request that all team members receive the newest quality standards training and review one another ' s work.

B.

Request that a quality specialist be assigned to the project to check the final product at the end of the project.

C.

Break down the project into several iterations and incorporate a quality check by a quality auditor in each iteration.

D.

Break down the project into several iterations and incorporate automatic testing and quality improvement sessions.

Page: 9 / 165
Total 2196 questions