Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMP Based on Real Exam Environment

Page: 9 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 33

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented.This may require a significantchange in the technical architecture and an additional release.

What should the project lead do first?

Options:

A.

Discuss with the solution architect

B.

Discuss with the development team

C.

Discuss with the product owner

D.

Discuss with the technical lead

Question 34

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous

project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely

finished in 8 months.

What should the new project manager do?

Options:

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client.

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Question 35

While following up on a deliverable, a team member expresses concern to the project manager about working with another team member. This team member states that the other team member, who is a functional manager, is often defensive and aggressive during meetings.

How should the project manager handle this situation?

Options:

A.

Report the disruptive team member to the human resource (HR) department.

B.

Suggest that the team member ignore the disruptive team member and focus only on the work.

C.

Monitor the situation for a few weeks to determine if the disruptive team member's attitude changes.

D.

Encourage both team members to meet as soon as possible and resolve the problem.

Question 36

A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and thestakeholder notices that an important functionality for their area was not tested.

Which tool should the project manager have used to prevent this situation?

Options:

A.

Project charter

B.

Stakeholder register

C.

Project scope statement

D.

Issue log

Page: 9 / 26
Total 354 questions