Summer Special Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 60certs

Pass PMP Exam Guide

Page: 11 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 41

At the end of a project, the project manager was asked to provide a performance rating of the project team members. What should the project managermainly make reference to?

Options:

A.

Competencies of team members

B.

Agreed-upon key performance indicators (KPIs)

C.

Feedback from the project sponsor

D.

Input from project stakeholders

Question 42

An intern is replacing a critical resource midway through a sprint. To help the intern get up to speed, the project manager assigns a senior engineer in the team as the

intern's mentor. Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

Options:

A.

Requested an experienced resource as a replacement

B.

Convinced the critical resource to remain on the project

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Question 43

During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract

end date. The contract is clear about the expiration of the service.

How should the project manager address this situation in order to close the project?

Options:

A.

Issue a change request and activate the formal change control process to address the situation.

B.

Escalate the request to the functional manager to approve the additional service hours.

C.

Deny the request and include it in lessons learned documentation for the next contract renewal.

D.

Accept the client's proposal to use the service until the additional hours are exhausted.

Question 44

A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the

transformation manager arises.

What should the project manager do to manage this?

Options:

A.

Analyze the context of the issue.

B.

Evaluate the influence of the parties involved.

C.

Lead the parties to find a compromise.

D.

Escalate the problem to the project sponsor.

Page: 11 / 26
Total 354 questions