Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Exam Questions and Answers PDF

Page: 19 / 149
Total 1988 questions

Project Management Professional (2025 Version) Questions and Answers

Question 73

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

Options:

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Question 74

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.

Question 75

A project manager for a construction site realizes the importance of stakeholder

relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.

What should the project manager do to customize the stakeholder engagement plan?

Options:

A.

Analyze stakeholder diversity in the community.

B.

Assess the need to collaborate with the community

C.

Analyze the need to negotiate with the community.

D.

Assess the information requirements of the community

Question 76

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.

B.

Conduct project reviews.

C.

Perform retrospectives.

D.

Complete sprint reviews

Page: 19 / 149
Total 1988 questions