Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Project-Management-Professional PMP Exam Questions and Answers PDF

Page: 19 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 73

A project manager is assigned to a project. There was a lot of conflict regarding the status of the project and compliance with international regulations. During a regular meeting, the sponsor wanted to know

how frequently the risks are being reviewed.

Which document project manager should check first?

Options:

A.

Risk management plan

B.

Risk register

C.

Issue log

D.

Risk report

Question 74

vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified

an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.

What should the project manager do next?

Options:

A.

Perform a cost-benefit analysis.

B.

Implement risk responses.

C.

Perform Integrated Change Control.

D.

Request a replacement resource.

Question 75

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The

project manager starts to present the budget, but the CEO suddenly asks to end the meeting.

What should the project manager have done to avoid this situation?

Options:

A.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register.

B.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting.

C.

Reviewed the communications management plan before inviting an external client representative to the meeting.

D.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting.

Question 76

A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project.

To what level should the project manager decompose their project?

Options:

A.

To the level where the highest level of quality is maintained

B.

To the lowest level where cost and duration can be estimated and managed

C.

To level four of the schedule for bridge construction

D.

To the level where the bridge can be constructed safely

Page: 19 / 26
Total 354 questions