Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Pass Using PMP Exam Dumps

Page: 20 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 77

A global program is being kicked off, and various distributed teams are involved in delivering the initiative.Besides planning and executingthe scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Videoconferencing

B.

Chat conversations

C.

Encrypted emails

D.

Phone conversations

Question 78

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should theproject manager do to fix theproblem and improve the quality?

Options:

A.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

B.

Create a reward system granting incentives to the team members who are able to catch more defects.

C.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems.

D.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones.

Question 79

In a complex development project with many clients and team members, there have been delays in completing the required work. What should the project manager do?

Options:

A.

Empower the team members to do their work.

B.

Inform the project sponsor about this situation.

C.

Work with the team to develop a risk response plan.

D.

Send an email to human resources (HR) about this situation.

Question 80

A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (WBS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.

What should the project manager do in this situation?

Options:

A.

Maintain the task assignments as planned and compress the other tasks to keep the project on schedule.

B.

Ask the team members to work overtime to finish the tasks on time according to the schedule.

C.

Keep the task assignments unchanged since the project management plan has been approved.

D.

Review the work allocation and reassign some tasks to shorten the critical path.

Page: 20 / 26
Total 354 questions