Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PDF PMP Study Guide

Page: 21 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 81

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified

the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

Options:

A.

Conducted periodic reviews with the manager on resource availability.

B.

Defined the skill requirements more clearly in the scope statement.

C.

Consulted with the installation team on a regular basis to check for conflicts.

D.

Asked the manager to follow the agreed-upon resource management plan.

Question 82

During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?

Options:

A.

Identify the resources that were responsible for the deliverable and request a team development plan.

B.

Update the risk register and implement the approved risk response plan for quality deviations.

C.

Update the issue log, identify the involved stakeholders, and assign resources to the corrective actions.

D.

Submit a change request to update the project quality requirements for the involved project deliverable.

Question 83

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is

below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Apply an agile approach to help improve team performance.

B.

Schedule a meeting and communicate the performance concern to the team.

C.

Study and determine the appropriate leadership style suitable for the team.

D.

Hirea project team leader who can influence the project team members.

Question 84

During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is

concerned about working overtime.

What should the project manager do to motivate the team?

Options:

A.

Crash the project schedule to ensure completion on time.

B.

Meet with the team members to review their roles and responsibilities.

C.

Introduce team-building activities to improve team performance.

D.

Negotiate with the client to reduce the changes in requirements.

Page: 21 / 26
Total 354 questions