Explanation: A resource management plan is a document that describes how the project resources will be acquired, allocated, monitored, and controlled throughout the project life cycle1. A resource management plan helps project managers to ensure that the project has sufficient and appropriate resources to complete the project work on time and within budget. A resource management plan also defines the roles and responsibilities of the project team members and the resource managers, and the processes and tools for managing resource availability, utilization, and performance2.
In this question, the project manager should have asked the manager responsible for the equipment delivery to follow the agreed-upon resource management plan, which would have specified the resource requirements, allocation, and schedule for the equipment installation. By following the resource management plan, the manager could have avoided the capacity issue for the installation team, or at least communicated it to the project manager in advance, so that the project manager could have taken corrective actions to mitigate the impact on the project schedule. The project manager should also have monitored and controlled the resource management plan throughout the project, and updated it as needed to reflect any changes or issues in the resource availability or demand3.
Option A is not the best answer because conducting periodic reviews with the manager on resource availability may not be enough to prevent the situation from happening.The project manager should have established a clear and formal resource management plan with the manager, and ensured that the manager followed it consistently and reported any deviations or problems.
Option B is not the best answer because defining the skill requirements more clearly in the scope statement may not be relevant to the situation. The scope statement is a document that defines the project scope, deliverables, assumptions, and constraints4. The skill requirements are part of the resource requirements, which are defined in the resource management plan, not the scope statement.
Option C is not the best answer because consulting with the installation team on a regular basis to check for conflicts may not be the project manager’s responsibility. The project manager should have delegated the responsibility of managing the installation team to the manager in charge of the equipment delivery, and relied on the manager to follow the resource management plan and report any issues or conflicts to the project manager. References:
- 1: PMBOK Guide, 7th edition, page 83
- 2: Resource Plan: The Ultimate Guide to Resource Planning5
- 3: PMBOK Guide, 7th edition, page 85
- 4: PMBOK Guide, 7th edition, page 77
- 5: Resource Plan: The Ultimate Guide to Resource Planning