Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Full Access PMI PMP Tutorials

Page: 15 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 57

An agile project team discovers that they are unable to implement a feature completely in the first iteration. The team believes it may not be able to complete the tasks in the

second iteration. The feature is a critical component that the customer has prioritized.

What should the team do?

Options:

A.

Reduce the scope of the feature to fit into one iteration and deliver it to the customer.

B.

Go back to the customer and explain that they cannot implement the feature completely in one iteration.

C.

Split the feature into smaller subfeatures, implement them, and then deliver them incrementally in multiple iterations.

D.

Ask the customer to simplify the feature so that it can be implemented in one iteration.

Question 58

project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved,theproject manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

Options:

A.

The deliverables that are performing well and those that need more work.

B.

Specialized reports created specifically for the meeting as per directions from the project sponsor.

C.

Potential changes to the project's strategy and the feedback from senior executives.

D.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.

Question 59

In an agile team, some of the team members are coming forward to ask for more autonomy on the project. What shouldthe project manager do in thissituation?

Options:

A.

Discourage this request, as it is for the management team.

B.

Encourage the team lead to make decisions.

C.

Discourage them as conflicts may be created.

D.

Encourage the team members to make decisions.

Question 60

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting market requirements.

What should the project manager do?

Options:

A.

Cancel the iteration and add the requested changes.

B.

Continue the iteration and add the requested changes.

C.

Continue the iteration and review the change with the customer.

D.

Cancel the iteration and meet with the product owner.

Page: 15 / 26
Total 354 questions