Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Full Access PMI PMP Tutorials

Page: 15 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 57

A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?

Options:

A.

Revise the project schedule and inform the stakeholders regarding any delays

B.

Revise the project estimates and meet with the project team to discuss delays

C.

Review the management reserve to identify any costs associated with the delays

D.

Review the contingency reserve to identify any delays to the project

Question 58

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

Options:

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Question 59

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

Options:

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Question 60

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

Options:

A.

Review the iteration backlog because the product definition has changed and needs tobe reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove thestories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in thebacklog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order tohandle the modifications as a change request.

Page: 15 / 152
Total 2040 questions