Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Full Access PMI PMP Tutorials

Page: 15 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 57

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

Options:

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Question 58

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Question 59

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

Options:

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Question 60

In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.

What should the project manager do?

Options:

A.

Submit a change request to leverage previous experience and manage the project using a predictive approach,

B.

Schedule a daily project definition meeting with the team to define the project scope before starting the execution.

C.

Start executing the project as the scope will be defined and redefined throughout the project.

D.

Obtain partial approval from the product owner to baseline the project scope plan before starting the execution.

Page: 15 / 160
Total 2134 questions