Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Full Version PMP PMI Exam

Page: 7 / 149
Total 1988 questions

Project Management Professional (2025 Version) Questions and Answers

Question 25

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

Options:

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Question 26

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

Options:

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Question 27

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

Options:

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Question 28

A technical lead has complained to the project manager about a team member's performance. The team member has repeatedly missed tasks that have put sprint commitments at, What should the project manager do?

Options:

A.

Remove the learn member from the team and hue a more skilled one

B.

Ask the technical lead to provide more training to the team member

C.

Ask the technical lead to discuss performance directly with the team member

D.

Meet with the team member to understand the situation and provide feedback.

Page: 7 / 149
Total 1988 questions