Question 25

A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high-speed internet

service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now

use a system running on a conventional dial-up service.

What should the project manager do next?

Options:

A.

Meet with management about their decision and ask them to get another project manager.

B.

Agree with management and continue working the project management plan.

C.

Replace some of the team members that work virtually to help the company save money.

D.

Evaluate the impact of this decision and communicate with management.

Question 26

Afew key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, theproject schedule is seriouslydelayed.

What should the project manager do?

Options:

A.

Request additional resources to be incorporated to the project team.

B.

Observe the project team and give them time to catch up before escalating.

C.

Review the issues and adjust the project plan to give a realistic schedule.

D.

Escalate to the project sponsor and seek alternatives to resolve the issue.

Question 27

A project manager finds a mistake with an important server acquisition. The acquisition was expected for a critical path activity but has not arrived yet, causing significant impacts on time and cost. The team member responsible for this activity argues that they sent several emails to the supplier but received no reply.

Which document should be used to help avoid this kind of situation?

Options:

A.

Statement of work (SOW)

B.

Escalation process

C.

Communications management plan

D.

Stakeholder register

Question 28

A project manager has commissioned a design study from a consulting firm to investigate a number of alternatives. The project managerhas a strict policy on the cost of the study and has established a number of cost triggers and trend analyses.

Which tool is the project manager using?

Options:

A.

Secureanalysis

B.

Time and materials (T&M) contract

C.

Earned value (EV)

D.

Control chart