Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Changed PMP Exam Questions

Page: 16 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 61

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?

Options:

A.

Reassign the task to another member of the team

B.

Support the team member by providing one more resource to complete the task immediately

C.

Ask the team member if there is an impediment and help to remove the blockers

D.

Keep the project sponsor informed about the delay

Question 62

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

Options:

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Question 63

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

Options:

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Question 64

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

Options:

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Page: 16 / 160
Total 2134 questions