Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Changed PMP Exam Questions

Page: 16 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 61

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project shouldbe stopped.

How should the project manager handle the situation?

Options:

A.

Have a discussion with the project sponsor and cancel the project.

B.

Have a discussion with the sponsor and recommend the project business value be reassessed.

C.

Remove the items no longer applicable from the backlog and present the backlog to the project team.

D.

Continue working on the defined scope and review the risk matrix.

Question 62

A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that

having the Scrum team in the workshops is a waste of time because the project was delivered successfully.

What should the project manager do?

Options:

A.

Ask the scrum master to attend the workshops.

B.

Ask the Scrum team members to share retrospectives.

C.

Invite the Scrum team members as mandatory participants.

D.

Invite the Scrum team members as optional participants

Question 63

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that could becomeunmanageable with time. What should the project manager do?

Options:

A.

Compare the cost of improving quality against the cost of failure and adjust the budget.

B.

Help the team create the definition of done (DoD) to improve delivery quality. 0 2 Add testing items to the backlog to assess quality periodically. oO

C.

Expand the team in order to improve the quality of the project.

Question 64

A project manager received a request to add features and functions to the project after the scope had already been established. What should the projectmanager do?

Options:

A.

Follow the stakeholder engagement process.

B.

Follow the risk management process.

C.

Follow the change management process.

D.

Follow the requirements management process.

Page: 16 / 26
Total 354 questions