Question 21

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a callfrom the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available.

This is going to significantly impact the deliverable.

What should the project manager do?

Options:

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

D.

Inform the customer of the impact immediately and prepare for escalation.

Question 22

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements. The former project manager gave the

new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

Options:

A.

Submit a change request to cover extra hours associated with project meetings.

B.

Speak with the client team member about the continuous delays during project meetings.

C.

Update the communications matrix to ensure that client team member is included.

D.

Increase the project meeting frequency and duration to allow for the extra work required.

Question 23

A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team member'sdeliverables do not meet the requirements.

What should the project manager do first?

Options:

A.

Discuss the process used to create the noncompliant deliverables with the project team to see if there was a potential misunderstanding.

B.

Meet with the project team to explain that noncompliant deliverables must be reworked and submitted immediately to avoid project delays.

C.

Schedule time with the project sponsor to inform them that the project schedule is slipping due to the time it will take to rework the deliverables.

D.

Assemble the project team via conference call to tell them that disciplinary action will be taken if any more noncompliant deliverables are submitted.

Question 24

A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor isvery keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.

How should the project manager address this situation?

Options:

A.

Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration.

B.

Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration.

C.

Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed.

D.

Ensure the feature has been included in the product backlog, explain to the sponsor the consequences of the request, and ask the team to include the features tasks in the next iteration.