Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Full Course Free

Page: 29 / 149
Total 1988 questions

Project Management Professional (2025 Version) Questions and Answers

Question 113

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Question 114

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor

B.

Workstream leader alone

C.

Workstream leader and functional manager

D.

Workstream leader and project management office (PMO)

Question 115

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

Options:

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Question 116

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Page: 29 / 149
Total 1988 questions