Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Vce PMP Questions Latest

Page: 33 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 129

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

Options:

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Question 130

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

Options:

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Question 131

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager ' s priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible

B.

Determine a mitigation strategy to move the project forward

C.

Take over contract negotiations for the team member to speed up the process

D.

Assist with the removal of impediments and blockers so that the project can continue

Question 132

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

Options:

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Page: 33 / 165
Total 2196 questions