Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI Project-Management-Professional PMP New Questions

Page: 18 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 69

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the

complexity of the work was underestimated.

What should the project manager do?

Options:

A.

Update the issue log and escalate it to the project sponsor.

B.

Ask to replace some team members with more experienced ones.

C.

Meet with the team to review internal actions to resolve the situation.

D.

Ask the technical manager to help the team with the issue.

Question 70

During the final stage of the launch for a new design, team members are having a conflict about some features of the design. What should the project manager do?

Options:

A.

Ask the project sponsor to make the decision about the design features.

B.

Call a stakeholder meeting along with team members and seek consensus.

C.

Ask stakeholders to reduce the scope in order to meet project deadlines.

D.

Review the design with the team members and propose a new launch date.

Question 71

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.

Send a daily retrospective report to all team members instead of holding standup meetings.

B.

Engage the project team in implementing and improving key aspects of the standup meetings.

C.

Include a daily brainstorming session in the standup meetings to resolve pending issues.

D.

Ask the product owner to remove team members who do not comply with standup meeting rules.

Question 72

A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.

What should the project manager do next?

Options:

A.

Review the stakeholder engagement plan.

B.

Add the needed manual and update the risk log.

C.

Review the terms and conditions of the contract.

D.

Submit a change request to include the manual.

Page: 18 / 26
Total 354 questions