Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

New Release PMP Project-Management-Professional Questions

Page: 26 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 101

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do toimprove project performance?

Options:

A.

Empower the team members to remove obstacles and blockers.

B.

Address and remove obstacles and blockers for the team.

C.

Ask stakeholders to communicate with the team directly.

D.

Add blockers to the issue log and risk management plan.

Question 102

A project manager for an IT company starts a project with members distributed across five different countries and four different time zones. In the first meetings with the sponsor and some stakeholders, theproject manager notices that people do not join the meetings on time, have internet connection issues, or experience language barriers during some conversations.

What should the project manager do to improve communication among the team?

Options:

A.

Setup a team communications management plan for the company and team members to follow immediately.

B.

Explain the benefits of common working hours to aid better communication among the project team.

C.

Share a contact log document for all the team members to make communication easier.

D.

Arrange for some initial face-to-face team meetings for the project team to meet each other.

Question 103

A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed.

During a recent external audit, the project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.

What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?

Options:

A.

Ensured that all the required approvals were received per the organizational procedures

B.

Ensured that all defects identified during testing were resolved before implementation

C.

Ensured that all of the required tasks identified in the scope were completed successfully

D.

Ensured that all documentation was completed post implementation before closing the project

Page: 26 / 26
Total 354 questions