Question 177

A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?

Options:

A.

Emphasize to the executives that the project manager was specifically requested for this project

B.

Schedule deliverables solely based on priorities and must-have-by dates, and gauge responses

C.

Hold a team meeting emphasizing existing governance policies and procedures

D.

Adopt a project framework aligned to the executives’ availabilities and then evaluate the risks

Question 178

During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?

Options:

A.

Assess the opportunities to deliver project value incrementally

B.

Gather all the requirements’ details and schedule a refinement meeting

C.

Prepare a project management plan for the full scope using an agile approach

D.

Approve a change request to change the project approach to agile

Question 179

A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?

Options:

A.

The interdependencies between the deliverables

B.

The business continuity plan of the deliverables

C.

The stakeholder engagement plan

D.

The user stories and story points

Question 180

An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?

Options:

A.

Execute the next iteration planning considering the quality issues.

B.

Schedule quality reviews to obtain stakeholder approvals and feedback.

C.

Confirm the right quality tests are applied before moving to the next iteration.

D.

Include all the quality problems found in the technical debt backlog.