Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 177

A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?

Options:

A.

Asked the customer to participate in project status meetings to better understand the progress

B.

Informed the project team to closely monitor the deliverables and keep the customer informed

C.

Reviewed benefits realization with the customer regularly and constantly aligned expectations

D.

Explained to the customer that the project is in good shape as the system is operational

Question 178

During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?

Options:

A.

Work with the product owner to ensure the product backlog is prioritized

B.

Review the project backlog during the team’s coordination meeting

C.

Encourage team members to prioritize the product backlog

D.

Ensure team members are working according to the project management plan

Question 179

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Question 180

A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately.

How should the project manager approach the software development life cycle with this customer?

Options:

A.

Raise a risk that the scoping and estimating phase of the project will be delayed if the customer cannot deliver an approved set of requirements.

B.

Add extra time to the estimating phase of the project as well as additional resources to accommodate the lack of requirements.

C.

Assign a business analyst to build a detailed set of requirements with the customer so the project manager can properly estimate the project duration.

D.

Explain to the customer that the team will build a production prototyping model to help the customer visualize how the additional features should work.