Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 189

A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?

Options:

A.

Commit to completing the deliverables associated with only the engaged parties.

B.

Submit a change request to extend the time needed to engage all of the parties.

C.

Request that the product owner define which parties should be engaged first.

D.

Prioritize the engagement of parties who are most impacted to minimize project risk.

Question 190

In a fixed time and budget project, the customer wants development of a core component to be based on agile practices because the final scope has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact project profitability. Which two controls should the project manager incorporate into the contract to address development of the core component? (Choose 2)

Options:

A.

Establish a governance committee to review contract delivery

B.

Require that only internal resources be utilized for this project

C.

Provide alternatives to scope change at specific project phases within the contract

D.

Tier the contract for fixed and agile components

E.

Limit the number of iterations for development in the contract

Question 191

A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department. What should the project manager do to align with this requirement?

Options:

A.

Perform a make-or-buy analysis

B.

Review the statement of work (SOW)

C.

Leverage the enterprise environmental factors (EEFs)

D.

Refer to the organizational process assets (OPAs)

Question 192

A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?

Options:

A.

Discuss the issue with the product owner

B.

Discuss this with the project team in the next sprint retrospective meeting

C.

Discuss this with the project team in the next sprint planning meeting

D.

Discuss this with the PMO manager