Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Download Latest PMP Questions

Page: 44 / 160
Total 2134 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 173

A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?

Options:

A.

Continue with execution since the project was successful up to this phase

B.

Call for business development to revalidate inputs at the next stage gate

C.

Provide the necessary analysis to enable examination of the business value

D.

Request a delay to the stage gate until business development provides the next update

Question 174

A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?

Options:

A.

Use management reserve and crash the schedule

B.

Implement an agile project delivery approach

C.

Explain the need to follow the quality assurance (QA) schedule to the customer

D.

Adopt an incremental project delivery approach

Question 175

A product owner asks a project manager for details about products that were added during the last iteration. What should the project manager do to gather this information and send it to the product owner?

Options:

A.

Evaluate the sprint backlog

B.

Evaluate the product backlog

C.

Evaluate the sprint increment

D.

Evaluate the product development cycle

Question 176

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?

Options:

A.

Validate completeness of the tasks delivered in the current sprint

B.

Increase team velocity to execute tasks for the next sprints

C.

Reassign the team member to other tasks in the current sprint

D.

Encourage the team member to execute the next sprint tasks

Page: 44 / 160
Total 2134 questions