Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Helping Hand Questions for PMP

Page: 24 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 93

A project manager is building a team to work on a service integration project that will transition technology management services from company A tocompany B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, havedifferent types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

Options:

A.

Organize the team members into several kick-off sessions based on technology type.

B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.

C.

Ask the human resources (HR) department to arrange interview meetings to select the team.

D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.

Question 94

On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project managerrealized that some of the keyactivities were scheduled over the holiday periods in the overseas offices.

What shouldthe project manager do next?

Options:

A.

Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.

B.

Request that the offices in overseas locations work overtime to mitigate schedule slippages.

C.

Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.

D.

Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.

Question 95

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around theproject has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.

B.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.

C.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.

D.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.

Question 96

An agile project is running its second iteration out of six. A marketing director, who is a key stakeholder, contacts the project lead for a highlevel report of the project.

What should the project lead do?

Options:

A.

Tell the stakeholder that a new report will be produced at the end of the iteration.

B.

Explain to the stakeholder that the key indicators are by iteration.

C.

Ask the product owner to develop the new report based on the iteration information.

D.

Develop the requested report based on the iteration information.

Page: 24 / 26
Total 354 questions