Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Helping Hand Questions for PMP

Page: 24 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 93

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization ' s project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

Options:

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Question 94

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

Options:

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project ' s quality management

D.

Determined a budget reserve for this project

Question 95

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country ' s economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do ' ?

Options:

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Question 96

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Options:

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Page: 24 / 165
Total 2196 questions