Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Newly Released PMI PMP Exam PDF

Page: 10 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 37

During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?

Options:

A.

Keep activities as planned regardless of the resource change.

B.

Update the burndown chart to reflect this resource's absence.

C.

Have a meeting with the resource to understand the issue.

D.

Request an additional resource to finish the project.

Question 38

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the

project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

Options:

A.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions. @]

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Question 39

A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.

How should the project manager resolve this issue?

Options:

A.

Ask the team to rework the definition of done (DoD) before items can be pulled into the backlog.

B.

Review issues and identify opportunities for improvement that add value to the product.

C.

Gather the project team and product owner to find a solution design.

D.

Assist the team in estimating project tasks such as milestones and story points.

Question 40

A project team member complained to the project manager that they are not sure if they are working on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past, they worked on a document for more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

Options:

A.

Implement a project management information system (PMIS).

B.

Encourage better team communication by positioning team members closer together.

C.

Update the communications management plan to ensure correct delivery of the latest version.

D.

Restrict team members from sending the requirements documents via email.

Page: 10 / 26
Total 354 questions