Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Newly Released PMI PMP Exam PDF

Page: 10 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 37

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?

Options:

A.

Analyze the communication needs of the stakeholders.

B.

Communicate the project details to the stakeholders.

C.

Communicate progress more frequently to the stakeholders.

D.

Introduce a separate stakeholder engagement meeting.

Question 38

A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

Options:

A.

Time and materials (T & M) with an agile approach

B.

Cost reimbursable contract with a predictive approach

C.

Fixed-price contract with a predictive approach

D.

Memorandum of understanding (MOU) with an agile approach

Question 39

A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.

What should the project manager do?

Options:

A.

Meet with the project sponsor and key stakeholders to confirm that the information about the forecasted project value is accurate.

B.

Ask the organization to cancel the project because the project manager is unable to confirm that the project will deliver the forecasted value.

C.

Proceed with execution of the project whether the information about the forecasted value is right or not because the project is already approved.

D.

Develop scope alternatives to achieve the forecasted project value in the event that project benefits information is inaccurate.

Question 40

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?

Options:

A.

Escalate the obstacle to a servant leader for resolution.

B.

Make changes to reprioritize the backlog because of the obstacle.

C.

Reject the obstacle and present the partial solution to the customer.

D.

Focus on generating business value despite the obstacle.

Page: 10 / 165
Total 2196 questions