Project Management Professional (2025 Version) Questions and Answers

Question 157

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

Options:

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

Question 158

An agile team has started a new project. When should the project manager organize their first team retrospective?

Options:

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

Question 159

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

Options:

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Question 160

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

Options:

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.