Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Project-Management-Professional PMP Book

Page: 23 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 89

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

Options:

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.

Question 90

A project manager is working on a highly complex project. During the execution of

the project, the local government changed certain environmental regulations, which could

potentially delay the project.

What immediate action should the project manager take?

Options:

A.

Update the issue log.

B.

Update the project baseline.

C.

Update the risk management plan.

D.

Update the change request log.

Question 91

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?

Options:

A.

Replan the remaining iterations according to the new installation dates

B.

Update the product backlog m order to address the delays

C.

Review the procurement agreements to address the situation

D.

Find another vendor who can fulfill the delivery dates

Question 92

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

Options:

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Page: 23 / 152
Total 2040 questions