Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Project-Management-Professional PMP Book

Page: 23 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 89

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the processes and procedures, the

project manager notices similarities to a previous project that experienced similar roadblocks. The project manager reviews the task schedule and finds that certain tasks are

well behind expectations. In speaking with the project team, the project manager confirms that the team is following the processes exactly.

What should the project manager do?

Options:

A.

Review the resources allocated to the project and change accordingly.

B.

Review and amend the processes to ensure only value-adding activities are present.

C.

Update the variation register to account for the extended project time.

D.

Update the schedule to account for the unexpected delays in the project tasks.

Question 90

A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources.

What strategy should the project manager implement to deal with this situation?

Options:

A.

Ask the team to accelerate the iterations and avoid interruptions.

B.

Verify team performance and ask for improvement during daily standup meetings.

C.

Recommend that the project sponsor increases the budget to bring new resources.

D.

Discuss the problem with the team and decide how to do the work together.

Question 91

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not

have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

Options:

A.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

B.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place.

D.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

Question 92

A project manager is assigned midway through a project. The team members are in different locations across the country and they are unable to meet in-person often. During a status review meeting, one of

the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

Options:

A.

Request the project team include the stakeholder's details and make sure the project status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder, and include the stakeholder’s needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Page: 23 / 26
Total 354 questions