Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Legit PMP Exam Download

Page: 51 / 149
Total 1988 questions

Project Management Professional (2025 Version) Questions and Answers

Question 201

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

Options:

A.

Finish to start

B.

Start to start

C.

Start to finish

Question 202

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

Question 203

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

Options:

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Question 204

A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall

progress.

What should the project manager do next?

Options:

A.

Capture this in the issue log and escalate it to the project sponsor.

B.

Meet with the stakeholder to understand what is causing the delays.

C.

Facilitate a brainstorming session to find potential workarounds.

D.

Discuss the need to influence this stakeholder with the sponsor.

Page: 51 / 149
Total 1988 questions