Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 197

A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.

What should the project manager do?

Options:

A.

Evaluate the new proposal with the project team to determine if it is a more beneficial alternative.

B.

Adhere to the issue response proposed in the risk management plan, as it is the agreed-upon solution.

C.

Ask the project team member to write a formal email explaining the proposal and send it to the change control board (CCB).

D.

Implement the new proposal as soon as possible, as it is supposed to be cheaper and equally effective.

Question 198

During daily team coordination meetings, team members constantly ask which tasks they should focus on first.

How should the project manager ensure the team is fully productive?

Options:

A.

Encourage project team members to prioritize the product backlog.

B.

Work with the product owner to ensure the project backlog is prioritized.

C.

Ensure team members are working according to the project management plan.

D.

Review the project backlog during the team’s coordination meeting.

Question 199

A project has a very demanding and sensitive business stakeholder who functions as a subject matter expert (SME). The project manager has assigned two different team members to work with the stakeholder. However, both team members have complained that the stakeholder is difficult to work with.

What should the project manager do first?

Options:

A.

Evaluate the situation and look for alternatives to improve communication with the stakeholder.

B.

Speak with the team members to collect details and write an email to the stakeholder requesting that they collaborate with the team.

C.

Raise the issue during a steering committee meeting and ask that the stakeholder change their attitude.

D.

Escalate the issue to the sponsor and request that they speak with the stakeholder.

Question 200

Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?

Options:

A.

Begin daily check-ins with the two vendors to recover time at their own expense

B.

Extend the project schedule and inform the vendors it was due to their poor performance

C.

Find replacements for the two vendors to complete the project in a timely manner

D.

Reduce the two vendors’ pay due to poor performance and lack of communication