Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 197

A project manager is leading a project with a risk management plan detailing strategy and actions if any identified risks become an issue. One of the identified risks becomes an issue, but the project manager believes the planned response may not be the best. What should the project manager do?

Options:

A.

Meet with the project team and sponsor to reevaluate all issue responses registered in the risk management plan

B.

Escalate the issue to the sponsor and register the new risk response in the project documents

C.

Adopt the action prescribed in the risk management plan since it was agreed to beforehand

D.

Submit a change request to perform a different issue response than what is registered in the risk management plan

Question 198

A new stakeholder is unaware of the existence of the project a few weeks before the final deliverable and project completion. What should the project manager do first?

Options:

A.

Escalate this issue to the project sponsor.

B.

Communicate the full details of the project activities to the stakeholder and solicit input.

C.

Analyze this stakeholder’s interest and impact.

D.

Share the summary of the project activities with the stakeholder and conclude the project.

Question 199

It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?

Options:

A.

Address the required changes in the next release

B.

Review and update the acceptance criteria

C.

Put more emphasis on the definition of done (DoD)

D.

Extend the iterations to complete the items

Question 200

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

Options:

A.

Meet with project stakeholders to define a mitigation plan

B.

Register the issue and escalate it to the project sponsor

C.

Estimate the cost of changing the project location

D.

Execute the contingency plan defined in the risk management plan