Project Management Professional (2025 Version) Questions and Answers

Question 197

A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager

schedules a meeting with the two stakeholders to resolve the issue.

What role does the project manager play in this situation?

Options:

A.

Accommodator

B.

Mediator

C.

Arbitrator

D.

Conciliator

Question 198

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

Options:

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Question 199

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

Options:

A.

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.

D.

Hired a third-party agile delivery team to do the implementation.

Question 200

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

Options:

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.