Summer Certification Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Questions Answers

Page: 8 / 165
Total 2196 questions

Project Management Professional (PMBOK 7th Version) Questions and Answers

Question 29

A project manager is working in a constantly changing business environment. In order to address this situation, the project manager has decided to use a collaborative leadership style.

Which landscape describes the project environment?

Options:

A.

High accountability, little authority

B.

Available resources, bad roadmaps

C.

Good roadmaps, little accountability

D.

Enough authority, insufficient resources

Question 30

A project team is using an iterative and incremental delivery approach. The sprint ' s duration is 1 month with a production release every 3 months. In the last sprint review, the users communicated that they want the functionality presented and deployed in 5 weeks. The project lead is working on the next release plan.

When should the project lead have their team deploy the functionality?

Options:

A.

In 1 month

B.

In 5 weeks

C.

In 12 weeks

D.

In 2 months

Question 31

A drone manufacturing company is designing its first drone. The new project architect has called the project manager to review the project scope. The architect wants to reshuffle the scope and schedule to test the drone functionality first. The project team disagrees because the scope has already been approved and any change might affect the timelines set by the CEO.

What should the project manager recommend?

Options:

A.

Review the timelines with the architect and invite the CEO to the meeting to make sure all the stakeholders are involved.

B.

Reject the review as the completed project timeline is set by the company ' s CEO and has already been approved.

C.

Agree to review the architect ' s new proposal to assess the impact on the timelines set by the CEO.

D.

Register an issue in the log regarding the timeline delay to the CEO ' s approved plans before agreeing to change the project scope.

Question 32

Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.

How should the project manager approach the situation?

Options:

A.

Intervene in the deliberation process and weigh in on which approach would be better to use.

B.

Deliberate with the team moving the item to the product backlog and taking up the next item in the list.

C.

Stop the deliberation process and ask the team to take a vote using the nominal group technique.

D.

Allow the team to continue deliberating until the team reaches a consensus on the desired approach.

Page: 8 / 165
Total 2196 questions