Big Halloween Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI PMP Questions Answers

Page: 8 / 152
Total 2040 questions

Project Management Professional (2025 Version) Questions and Answers

Question 29

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Question 30

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

Options:

A.

Submit a change request to adapt the objectives of the project to the current situation

B.

Ask the scrum master to refine the user stones to improve the team members' understanding

C.

Find and provide training to the project team members who do not have the required skills

D.

Extend the duration of standup meetings to include skill transference from trained to untrained members

Question 31

A project manager became aware of misunderstandings between a key stakeholder

and a team member with regard to some of the features defined in the project scope. What

should the project manager do?

Options:

A.

Reconcile the key stakeholder to the team member's recommendation.

B.

Reconcile the team member to the key stakeholder's recommendation.

C.

Escalate the communication concerns to the project management office (PMO) andrequest that they take action

D.

Work with both the team member and the key stakeholder to reach a consensus.

Question 32

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion

B.

Conflict resolution

C.

Emotional intelligence

D.

Negotiating

Page: 8 / 152
Total 2040 questions