Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI PMP Questions Answers

Page: 8 / 26
Total 354 questions

Project Management Professional (2023 Version) Questions and Answers

Question 29

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed

concerns about the use of new tools on such an important project.

What should the project manager do?

Options:

A.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

B.

Review the adaptive tools' impact and obtain agreement from the functional manager.

C.

Follow the functional manager's recommendation to implement only predictive tools in the project.

D.

Make the decision on which project approach to use that would best fit the project.

Question 30

A company plans to initiate a project involving a new technology. Approval for the project is required.

What should the project manager do?

Options:

A.

Review the cost and schedule baselines for execution.

B.

Identify the risks in implementing the new technology.

C.

Define change management for the new technology.

D.

Analyze the cost and identify the project benefits.

Question 31

A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a lowperforming team. In order to get the project back on track, what should the project manager do first?

Options:

A.

Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.

B.

Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule,

C.

Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.

D.

Begin holding daily meetings to assign each team member discrete tasks with specific due dates.

Question 32

A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand

for this product and wants it to launch as soon as possible.

What should the project manager do to realize this opportunity?

Options:

A.

Hire a third party who is an expert on the industry's regulations to work out the details.

B.

Escalate the issue to the company's CEO who has experience with the regulations.

C.

Communicate with the industry's regulatory authority to grant the company an exception.

D.

Comply with the regulatory requirements and work to compress the project schedule.

Page: 8 / 26
Total 354 questions