Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI Agile PMI-ACP Book

Page: 8 / 8
Total 208 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 29

A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.

What should the Scrum Master do?

Options:

A.

Point out that the team chose to work on other requirements to speed up the project

B.

Ensure that the product owner reviews the contents of the information radiator

C.

Ensure that the next sprint planning meeting reviews the satisfaction histogram

D.

Point out that it is the responsibility of the product owner to clarify requirements

Question 30

During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?

Options:

A.

Add this threshold requirement request as acceptance criteria in all impacted stories

B.

Create a spike story to analyze the impact of the threshold requirement on current stories

C.

Conduct design planning session to review the performance threshold requirement

D.

Identify the tasks for the new performance threshold requirement

Question 31

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Question 32

A product owner asks a newly formed scrum team how many story points will be completed in a sprint. What should the scrum master do?

Options:

A.

Engage the team to determine the sprint velocity based on previous agile projects.

B.

Average the sprint velocity based on input from team members

C.

Share the sprint velocity obtained from the sponsor with the team

D.

Run multiple sprints before determining the sprint velocity with the team.

Page: 8 / 8
Total 208 questions