Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free PMI-ACP PMI Updates

Page: 31 / 36
Total 476 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 121

Senior management is frustrated at the lack of a detailed implementation plan that shows exactly when the project will end and when all requirements will be met. The team has been using a rolling wave planning approach so far on the project.

How should the agile practitioner explain to senior management the benefits of this approach?

Options:

A.

It ensures a consistent level of detail is available in the project schedule

B.

It prevents a wasteful buildup of requirements inventory that may never be processed

C.

It provides a concrete definition of project scope, cost and duration

D.

It allows the team to lock down the stories to be included in a release

Question 122

During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk.

What should the team do next?

Options:

A.

Work overtime to meet the customer request and the iteration commitments.

B.

Ask another team that is less busy to handle the situation.

C.

Work with the product owner to assess the impact for reprioritization.

D.

Work on the customer request in the next iteration as a top priority.

Question 123

After a successful product deployment, a key stakeholder informs an agile team member that an implemented feature is failing to deliver its expected business value. The team member replies that the requirement was provided by the customer, and that the scope was clearly met.

If the problem were an issue of requirement elicitation rather than delivery, what should have been done to avoid this situation?

Options:

A.

Stakeholders should have regularly been engaged to obtain feedback and reduce the functionality risk.

B.

The team should have used the lean principle of delay, so that actual facts could be considered rather than assumptions and predictions.

C.

Interdependent teams should have been engaged using a collaborative approach to identify and leverage the best support.

D.

An owner should have been identified to obtain timely stakeholder feedback.

Question 124

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the Scrum Master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the Scrum Master respond to this request?

Options:

A.

Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend.

B.

Create and update bi-weekly project status reports for the stakeholder who requested the report.

C.

Escalate this to the stakeholder's supervisor because this is an unreasonable request.

D.

Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

Page: 31 / 36
Total 476 questions