PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 57

The Agile team has failed to meet their iteration goal, and contention has developed between members. The Agile Leader would like to determine how to improve the team’s productivity and morale.

How should the Agile Leader address this?

Options:

A.

Standup meeting

B.

Retrospective meeting

C.

Demo of the new features to energize the team

D.

Offsite meeting with stakeholders

Question 58

How can the scrum master respond to a stakeholder who suggests using velocity as a metric to measure team efficiency in an agile project?

Options:

A.

Velocity of a Scrum team will stop once it becomes stable and only then the team will become efficient with its deliverables.

B.

Velocity can only measure if a Scrum team has a stable and predictable run rate but not whether or not they are delivering better deliverables efficiently.

C.

Velocity will become more predictable only in stable teams and velocity should not be measured in Scrum teams until that occurs.

D.

Velocity is a great way of measuring the Scrum team's efficiency, and a stable velocity means the team is predictable and efficient.

Question 59

Following a successful product release, senior management asks an agile team how to improve the value of the product for the next release.

What should the team do?

Options:

A.

Conduct frequent demos and obtain feedback from users throughout the development of the next release

B.

Inform senior management that since the product was successfully released, the project is considered delivered and should be closed

C.

Request additional budget to implement a Scrum of Scrums approach to scale the teams and add capacity

D.

Implement a better definition of done to ensure that continuous integration processes are managed effectively

Question 60

There is a throughput of 200 tickets in a customer service line. The tickets are raised by employees, with each 8-hour shift averaging 50 tickets in progress.

What is the cycle time to resolve a ticket?

Options:

A.

0.25 hour

B.

1 hour

C.

2 hours

D.

4 hours