PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 13

What should the agile project leader do?

Options:

A.

Bring up the new member's impediments at the next meeting to demonstrate team support of input

B.

Assure the new member that inputs on impediments are valued and demonstrate this at the next meeting

C.

Have a senior lead work with the new member to avoid a negative impact on team productivity

D.

Privately work with the new member to address any impediments

Question 14

What should a product owner do when a new stakeholder is complaining that they are not receiving the relevant financial data regarding the project.

Options:

A.

Work with the scrum master to give the stakeholder access to the related information radiator

B.

Invite the stakeholder to the next sprint planning session so they can ask questions of the team

C.

Ask the team to prepare the requested data in the next iteration

D.

Direct the stakeholder to the project team so they can provide more data

Question 15

A healthcare agency has contracted a vendor to provide a financial accountability solution. During a daily coordination meeting, the lead developer reports they cannot complete the stories for this iteration because the project director requested a document detailing all testing planned for the solution. The team lead met with the project director to discuss alternatives but insists they need the detailed plan by the end of that week. The team lead advises the lead developer to continue coding.

What should the team lead do next?

Options:

A.

Negotiate with the project director to reduce the types of tests for which they need details to reduce the impact of this request.

B.

Escalate this as an issue to the executive project sponsor for a decision because it will impact the ability of the team to deliver the product on time.

C.

Ask the test manager to provide a detailed estimate of the time required to write the plan for the solution and their capacity for the remainder of the week.

D.

Ask the team to put their work on hold and collaborate on the documentation because it can be completed quicker if everyone shares the work.

Question 16

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.