Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-ACP VCE Exam Download

Page: 5 / 8
Total 208 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 17

An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?

Options:

A.

Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Question 18

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Question 19

The scrum master for a large project must provide an estimate of what can be delivered in six months What should the scrum master do?

Options:

A.

Commit to a specific feature set for delivery

B.

Explain that a commitment will be provided after planning

C.

Have the team estimate in story points to commit to a specific set of features

D.

Use the team's historical velocity to calculate a range of features that can be delivered

Question 20

A newly formed scrum team wants to foster an environment of transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments Emphasis is placed on how issues are resolved and the strategies for preventing them in the future Over time what will be the result of this approach?

Options:

A.

Kaizen

B.

Specific measurable, assignable, realistic and time-based (SMART) goals

C.

Key performance indicators (KPIs)

D.

Muda

Page: 5 / 8
Total 208 questions