Question 101

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Question 102

What should the agile practitioner do?

Options:

A.

Defer starting the design of item B until the second iteration is being planned

B.

Proceed with the design of item B, since it will hasten the second iteration

C.

Escalate the issue to the customer, and obtain their approval before starting the design of item B

D.

Log the issue in the risk register, and request change control board (CCB) approval

Question 103

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?

Options:

A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.

B.

Collect updates from each team member before the meeting and share them with all members.

C.

Ask the team member to update daily progress on the information radiators.

D.

Change the team velocity to show positive progress in shared information radiators.

Question 104

What should the agile project leader do?

Options:

A.

Re-estimate the project.

B.

Finish the product as it was initially planned.

C.

Try to include as many changes as possible.

D.

Ask the product owner for approval to proceed.