Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PMI Agile PMI-ACP Release Date

Page: 7 / 36
Total 476 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 25

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Question 26

Toward the end of a project, the product owner discovers that the project has a high probability of failure due to a critical feature not functioning as expected.

What should the product owner do?

Options:

A.

Terminate the project to cut losses

B.

Review possible options and make an informed decision to cut losses based on delivered business value

C.

Bring in experts to increase the probability of success

D.

Continue the project, release the product without the failing feature, and fix the feature in a subsequent release

Question 27

The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic.

What should the junior team member do?

Options:

A.

Speak to the agile lead about the concerns.

B.

Follow the agile lead's instructions.

C.

Increase the time worked to meet objectives.

D.

Speak to all team members about the concerns.

Question 28

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Page: 7 / 36
Total 476 questions