Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI Agile PMI-ACP Release Date

Page: 7 / 8
Total 208 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 25

The risk profile of a project has increased beyond the upper threshold of tolerance. The product owner and project leader meet to discuss an approach for dealing with this.

What should the team do next?

Options:

A.

Add risk mitigation tasks to the backlog, then prioritize in current and upcoming sprints

B.

Add risk mitigation time to each requirement

C.

Apply the 80/20 rule, reserving 20 percent of each sprint’s capacity for risk mitigation

D.

Hold all risks until they become issues, then add issue resolution tasks to the product backlog

Question 26

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope the team plans to work only on spike user stories for the next three sprints

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints.

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after all

spikes are executed

Question 27

An agile team member identifies a potential problem within the project team How should the team's coach react?

Options:

A.

Document the problem, escalate to the project manager and develop a solution for the team

B.

Add the problem to the backlog and assign resolution to a future iteration

C.

Instruct the team to try to solve the problem within the team

D.

Perform root cause analysis and report the problem to the product owner

Question 28

The team underestimated the complexity of a story, resulting in new decomposition of the work to be delivered in the current sprint and items to be returned to the backlog. What should the Scrum Master do next?

Options:

A.

Ask the project manager to work with the product owner to help generate clearer stories in the future.

B.

Develop guidelines to prevent future occurrences.

C.

During the retrospective, discuss the issue and create an action plan to avoid it in the future.

D.

Allow the team to devise a corrective action without external intervention.

Page: 7 / 8
Total 208 questions