The correct answer is D – Provide a delivery range based on the team's estimated velocity.
In Agile, planning is iterative and inherently uncertain. Rather than committing to a fixed schedule, it is best practice to provide a forecasted delivery window based on the team’s actual measured velocity. This reflects the inspect-and-adapt mindset of Agile.
From the PMI Agile Practice Guide:
“Agile teams forecast delivery using velocity ranges derived from completed work. Ranges reflect uncertainty and promote realistic expectations with stakeholders.”
(PMI Agile Practice Guide, Section 5.4 – Adaptive Planning)
Mike Griffiths affirms:
“Planning with ranges rather than fixed commitments respects the uncertainty of estimates and the empirical nature of Agile delivery. Forecasts should be based on velocity trends and updated iteratively.”
(Mike Griffiths, PMI-ACP Exam Prep Book, Chapter 5 – Adaptive Planning)
Why the other options are less suitable:
A suggests triangulating data but wrongly implies a precise commitment.
B is more of a work preparation activity, not a planning technique.
C (analogous estimation) is better suited for initial planning, not for an in-progress agile project with real velocity data.
Answer: D
══════════════════════════════════════════════════