PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 125

A manufacturing shop is using Kanban to plan, visualize workflow, and limit work in process (WIP). Which productivity key performance indicator (KPI) should the team lead be monitoring on a regular basis?

Options:

A.

Lead time

B.

Team velocity

C.

Burndown rate

D.

Earned value (EV)

Question 126

A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.

What should the product owner include in the release plan to achieve this?

Options:

A.

The objective, iterations and underlying features, iteration timelines, other pre-release activities, dependencies, and responsible team.

B.

The key objectives and a brief description of each user story to be delivered in each iteration release timelines and release dependencies

C.

The developer who will work on a specific feature and key DevOgs engineering activities to be performed during each iteration for the code integration.

D.

The sequence of user stories to be developed in each iteration, along with their start and end timelines, dependencies, and responsible team.

Question 127

A seven-member agile team's composition varies considerably in age, gender, culture, personality type, and professional background. When planning a team-building event, what type of interpersonal skills should the project leader use?

Options:

A.

Networking

B.

Social awareness

C.

Communication

D.

Leadership

Question 128

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team's agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration