Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Exactprep PMI-ACP Questions

Page: 35 / 36
Total 476 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 137

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Question 138

The product owner is very concerned about work not being completed and tested before a hard release date.

What can the agile team do to mitigate this risk?

Options:

A.

High-risk features can be prioritized to fit into releases with less work in progress.

B.

Low-risk, low-value features can be prioritized and completed first.

C.

High-risk, low-value features can be evaluated by the team early in the release.

D.

The work in progress can be adjusted to get more reviews with high-risk features.

Question 139

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?

Options:

A.

Review any reports of conflict between each of the team members over the last two years, and select only those with a track record of working well together.

B.

Ensure there is a balanced mix of people who are experts and members with broad experience based on the work to be performed and determine training needs.

C.

Ensure that none of the team members are geographically dispersed so that all team members can be colocated.

D.

Review each team member's contributions to the velocity of their previous projects and select the highest performers.

Question 140

An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager.

What should the Scrum Master do?

Options:

A.

Dismiss the team member

B.

Discuss the situation with the functional manager

C.

Report the functional manager to the project sponsor

D.

Demand that the functional manager respect the project charter

Page: 35 / 36
Total 476 questions