Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

PDF PMI-ACP Study Guide

Page: 19 / 36
Total 476 questions

PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Question 73

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

Options:

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Question 74

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

Options:

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Question 75

A new project is scheduled to begin next month. The project manager has had plenty of time to review and plan all the activities and has adopted the best approach for the project and the organization.

Which action did the project manager most likely take when choosing the approach?

Options:

A.

They most likely used a process that was successfully used for other projects; what has worked before is less likely to fail.

B.

They most likely discussed the best approach for this project with the team and will adapt and tailor the approach periodically by reviewing and verifying the scope with the customer.

C.

They most likely requested an increase in the management reserve; this will help the project manager to be more flexible during change requests and risk response activities.

D.

They most likely implemented a predictive approach; this approach might limit the freedom of making changes but secures the project from unknown risks.

Question 76

During a recent sprint review meeting with stakeholders, the product owner received detailed feedback indicating the critical changes needed for upgrading the legacy system to better align with the latest technologies and user needs. How should the product owner help ensure the product backlog is effectively managed, while helping the team remain focused? (Refer to the Product Backlog Exhibit)

Options:

A.

Prioritize the stakeholder feedback, considering the impact on strategic objectives and current workload, and discuss these priorities with the team in the next sprint planning meeting to collaboratively decide on the next steps.

B.

Implement the changes in the current sprint, reallocating resources and adjusting the sprint goals to accommodate the feedback immediately, regardless of the current workload and potential impact on ongoing tasks.

C.

Update the product backlog immediately without consulting the team, ensuring that the most critical feedback is addressed as soon as possible, even if it disrupts the current workflow.

D.

Disregard the feedback until the next product release, focusing solely on the current sprint commitments to avoid any disruption and maintain the current workflow, even if it means delaying potentially valuable changes.

Page: 19 / 36
Total 476 questions