Which of the following is a part of change control?
Requests for change are realised.
Requests for change are mitigated.
Requests for change are evaluated.
Requests for change are resolved.
Which one of the following best defines a benefit?
A. positive result of stakeholder management.
The successful management of a project.
An improvement resulting from project deliverables.
The successful delivery of project reports and updates.
Which one of the following best describes users?
Providers of both strategic and tactical direction to the project.
Those intended to receive benefits or operate outputs.
Facilitators of an appropriate issue resolution procedure.
Those providing full-time commitment to the project.
Which one of the following is the best reason for splitting a project into phases?
For team members to reflect on their performance during a phase.
For the project manager to take a break between phases.
It creates a decision point for continuing the project.
In order for the plan to be updated regularly.