Question 57

Quality management ensures that ______ are fit for purpose.

Options:

A.

processes and outputs.

B.

standards and benefits.

C.

managers and teams.

D.

regulations and requirements.

Question 58

Which one of the following statements best describes resource scheduling?

Options:

A.

A. process which identifies activities that will need project resources.

B.

A. process to assign roles to project resources.

C.

A. process that identifies when resources are needed.

D.

A. process to estimate the project resources.

Question 59

Which one of the following statements best defines a portfolio?

Options:

A.

A. group of related projects, which may include business-as-usual activities, that delivers change.

B.

A. timetable of how project activities and project milestones are planned over a period of time.

C.

A. group of projects that represent the delivery of all, or a discrete part of a new capability.

D.

A. grouping of an organisation's projects, programmes and related business-as-usual activities.

Question 60

Which of the following disadvantages applies to video conferencing?

Options:

A.

A level of technological expertise is required.

B.

Body language can reinforce the message.

C.

It is harder to maintain concentration.

D.

There are increased costs of getting to the meeting.