APM Project Fundamentals Qualification (PFQ) Questions and Answers

Question 65

Which of the following are the major stakeholders of the project management plan?

1) Project sponsor

2) General public

3) Project team

4) Project manager

Options:

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4

Question 66

An Organisational Breakdown Structure (OBS) is used to identify:

Options:

A.

the reporting structure and current availability of all individuals in the project.

B.

technical ability and line of communication for all individuals in the project.

C.

lines of communication and responsibility for all the individual managers in the project.

D.

the reporting structure and lines of communication for all individuals in the projects.

Question 67

Which one of the following takes place during closeout?

Options:

A.

Benefits realisation review.

B.

Final project review.

C.

Deliverables accepted by sponsor.

D.

Handover of relevant documentation

Question 68

A project manager would use a cost breakdown structure to produce:

Options:

A.

the cost of a do-nothing option.

B.

an analytical estimate.

C.

high-level project costs.

D.

a comparative estimate.