Question 93

A project manager has a team member who is creative, unconventional and good at solving problems, but who doesn't always concentrate on details or communicate well. According to Belbin's model, which team role will best use this person's qualities?

Options:

A.

Completer-Finisher.

B.

Plant.

C.

Monitor-Evaluator.

D.

Specialist.

Question 94

One purpose of risk management is to:

Options:

A.

adapt the plan to resolve problems.

B.

minimise threats and maximise opportunities.

C.

continually improve the project teams' efficiency.

D.

manage variations in a controlled way

Question 95

Which of the following is not an output of a critical path analysis?

Options:

A.

Total and free float.

B.

Earliest start time and latest finish time of activities.

C.

Project completion time.

D.

Cost-benefit analysis.

Question 96

Which of the following statements explain the importance of clearly defined success criteria at handover?

1) Deliverables are more likely to satisfy the client

2) The project can be effectively evaluated

3) Work can be effectively planned

4) Change can generally be avoided

Options:

A.

1 and 2

B.

1 and 3

C.

2 and 3

D.

2 and 4