How many dimensions are included in the business case?
Five
One
Three
Four
Resource levelling seeks:
to schedule activities within the limits of their float.
to minimise the use of overtime and weekend working.
not to exceed the limits of resource available.
to increase the resource availability
What is the main objective of A. RAM?
To provide a clear and concise summary of tasks or deliverables and the specific. responsibilities defined.
To provide an outline of the reporting structure to assist in day-to-day management of the project.
To provide an outline of the scope of the project and the specific deliverables that have been agreed for the project.
To provide an outline of the specific costs of the project and which key deliverables they are allocated to.
Who would be typically described as the person or organisation best placed to deal with a risk?
Risk manager.
Sponsor.
Project sponsor.
Risk owner.