APM Project Fundamentals Qualification (PFQ) Questions and Answers

Question 49

Which of the following statements refers to how scope is managed in a linear project but not an iterative project?

Options:

A.

Teams can act on new knowledge to change the scope.

B.

Teams can re-prioritise requirements within the scope.

C.

The scope of work is the starting point for the implementation of change control.

D.

Scope definition is assumed to be fixed for the whole project

Question 50

A communications plan should be:

1) one way

2) adjustable

3) measurable

4) rigid

Options:

A.

2, 3 and 4

B.

1 and 3

C.

1, 2 and 3

D.

2 and 3

Question 51

At which stage, in the Tuckman team development model, are team members clear and comfortable with their roles and responsibilities, and the project manager starts to see signs of the team working together?

Options:

A.

Storming.

B.

Forming.

C.

Norming.

D.

Performing

Question 52

While carrying out quality management for the project, you have been assigned the task of determining the quality standards that are applicable and how they should apply. Which part of quality management would best describe this activity?

Options:

A.

Quality planning.

B.

Quality assurance.

C.

Total quality.

D.

Quality control.