Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Last Attempt APM-PFQ Questions

Page: 16 / 31
Total 409 questions

APM Project Fundamentals Qualification (PFQ) Questions and Answers

Question 61

We have an expert-written solution to this problem!

Who has ultimate responsibility for project risk?

Options:

A.

Steering group.

B.

Risk owner.

C.

Project sponsor.

D.

Project manager

Question 62

What is the main reason for having an extended life cycle?

Options:

A.

Allow the project to have extra time to ensure that that there is enough capacity to realise benefits.

B.

Allow upfront planning for any supplemental activities and incorporate additional considerations for benefits realisation.

C.

Allow time for stakeholders to decide how they will use the output to best effect that will realise benefits.

D.

Allow extra funding to be applied to the project to ensure that sufficient resources exist to maximise benefits realisation.

Question 63

What would be a most likely result for an organisation following a PESTLE analysis?

Options:

A.

The organisation would know what political change is most likely and therefore the impacts on objectives considered.

B.

The organisation would most likely have a number of options available as to how the desired objectives could be achieved.

C.

The organisation would have an understanding of the necessary skills required to deliver the objectives required.

D The organisation would be able to develop an accurate estimate of the costs and time frame forthe objectives to be achieved.

Question 64

One difference between a project and business as usual is:

Options:

A.

projects achieve specified benefits but business as usual has only vague benefits.

B.

projects drive change whereas business as usual continues existing activities.

C.

projects have tightly controlled budgets whereas business as usual does not.

D.

projects have unclear deadlines but business as usual has multiple milestones

Page: 16 / 31
Total 409 questions